Construction, operation, maintenance and eventual decommissioning of up to a 15MW Solar Farm comprising the construction of solar panels mounted on metal frames, invertors, spares container, substation, auxiliary transformer, DNO substation, new access tracks, underground cabling, perimeter fencing with CCTV cameras and access gates, temporary construction compound, landscaping, and all ancillary grid infrastructure and associated site works Data via plota.co.uk
Last checked
Planning committee
Decided by Kings Lynn Planning Committee on 6 Oct 2025.
Approved by 8 votes to 4
As officers recommended.
- Officers advised approval because renewable-energy benefits outweighed limited, temporary harm, with impacts addressed through conditions.
- The parish council requested community funding and biodiversity measures, while five objections raised concerns about farming, landscape, wildlife and traffic.
- The committee approved the application by 8 votes to 4, with one abstention, subject to amended conditions 2 and 6.
Source: Plota analysis of Kings Lynn's committee minutes of 6 Oct 2025.
Site constraints 2
Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.
Plota Sites searches every land parcel in England and Wales: 29,327 sites fit this search. On and off the market, free to search.
Every application in Kings Lynn - and every UK council - as a live feed, an API, or a bulk CSV export.
Kings Lynn is one of the fastest councils in England for householder decisions, ranking #20 out of 296. Only 27% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).