Faizan-e-bahu Centre, Land To Rear Of 452 Westgate Road And Land At 26 Lewis Drive, Newcastle Upon Tyne, NE4 9JR Data via plota.co.uk

2024/1871/01/DET - Detailed Application Approved

Proposal

Erection of a three storey building for combined community centre and place of worship with ancillary living space (Class F1), associated improved landscaping, car/cycle parking, access and pedestrian link from Lewis Drive (Retrospective) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
25 Nov 2024
✓
Validated
16 Jan 2025
✓
Approved
5 Mar 2026

Approved on 5 Mar 2026 · Delegated decision · Last checked 30 Sept 2026

Documents 37

All documents on the council site ↗

Site constraints 2

Coal mining development high risk area
Recorded coal mining features at or near the surface. Most planning applications here need a coal mining risk assessment.
From the Mining Remediation Authority, formerly the Coal Authority. The development high risk area marks recorded coal mining features at or near the surface: mine shafts and adits, shallow workings, mine gas and former opencast sites. Most planning applications there need a coal mining risk assessment; householder applications, changes of use and some minor works are exempt. Mine entry positions come from old plans and can be out by several metres, and unrecorded workings can exist anywhere in the coalfield.
Coal mining risk assessments ↗
Also on the record
Inside the Newcastle upon Tyne built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Newcastle upon Tyne - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Detailed Application
Postcode
NE4 9JR
Received
25 Nov 2024
Validated
16 Jan 2025
Ward
y_Wingrove (up to May 2026)
Parish
Not Within A Parish Boundary
Case officer
Show
Target decision
6 Mar 2026
Decision
Grant Conditionally
Decision date
5 Mar 2026
Decision level
Delegated decision
Applicant
Show

How this decision compares

Decided in 413 days from validation, 346 days slower than Newcastle upon Tyne's median of 67 for community buildings. Approved, as 90% of community buildings here are.

47%decided within 8 weeks
90%approved
16%go to committee

Plota live figures for community buildings decided by Newcastle upon Tyne in the last twelve months, from validation. Newcastle upon Tyne decision record →

Consultation & key dates

Statutory expiry
6 Mar 2026
Newcastle upon Tyne
Planning Authority Score
4.9/10
Below average
#154 of 296 overall
Relevant to this application:
Householder decisions

Newcastle upon Tyne is slower than most councils at deciding householder applications: #205 of 296 on speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Newcastle upon Tyne decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #113 of 296
95%
Householder approved
Above avg (90%) #86 of 296
56%
Decided in 8 weeks
Below avg (63%) #205 of 296
42%
Extended time limit
Above avg (41%) #165 of 296
84%
Minor dwellings approved
37 decided (1-9 homes)
95%
Major dwellings approved
22 decided (10+ homes)
71%
Change of use approved
70 decided
1,005
Total decisions
103 refused in the year to March 2026