Skylark Garden Centre And Country Store Manea Road Wimblington March Cambridgeshire PE15 0PE Data via plota.co.uk

F/YR25/3077/COND - Discharge of condition Approved

Proposal

Details reserved by Condition 3 (Materials - in respect of lodges only), 5 (Access), 8 (Surface Water Drainage), 9 (Surface Water Run-Off), 11 (Lodge Positions), 12 (Ecology Survey), 13 (CEMP), 14 (Ecology Design) and 16 (Soft Landscaping) of planning permission (Variation of condition 6 (access) of planning permission (Erect 67 x holiday lodges, a toilet block, a reception building with associated parking and landscaping, and extensions to existing garden centre building and car park) - continue to use both access points) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
30 Jun 2025
✓
Validated
3 Jul 2025
✓
Consultation
26 Nov 2025
✓
Approved
23 Dec 2025

Approved on 23 Dec 2025 · Delegated Decision · Last checked 15 Nov 2026

Documents 118

Statements & assessments 27

PDF FDC ECOLOGY OFFICER Consultee Comment · 18 Dec 2025 View ↗ PDF ECOLOGY COMMENTS Consultee Comment · 4 Dec 2025 View ↗ PDF CCC LEAD LOCAL FLOOD AUTHORITY Consultee Comment · 14 Nov 2025 View ↗ PDF REV B COND 14 - ECOLOGICAL DESIGN STRATEGY Report · 14 Oct 2025 View ↗ PDF 21146-216 P2 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT F Drawing · 18 Sept 2025 View ↗ PDF 21146 101 P4 COND 8 - GARDEN CENTRE EXTENSION - DRAINAGE STRATEGY Drawing · 18 Sept 2025 View ↗ PDF 21146-200 P02 COND 8 - DRAINAGE DESIGN FOR CATCHMENT 1 Drawing · 18 Sept 2025 View ↗ PDF CCC LEAD LOCAL FLOOD AUTHORITY Consultee Comment · 18 Aug 2025 View ↗ PDF FDC ECOLOGIST Consultee Comment · 24 Jul 2025 View ↗ PDF COND 12 - SKYLARK ECOLOGY SURVEYS 2025 Report · 3 Jul 2025 View ↗ PDF COND 13 - SKYLARK CEMP BIODIVERSITY Report · 3 Jul 2025 View ↗ PDF COND 14 - SKYLARK - ECOLOGICAL DESIGN STRATEGY 2025 CANCELLED · 3 Jul 2025 View ↗ PDF 21146-102 REV P2 COND 8 - RECEPTION - DRAINAGE STRATEGY Drawing · 3 Jul 2025 View ↗ PDF 21146-101 REV P3 COND 8 - GARDEN CENTRE EXTENSION - DRAINAGE STRATEGY CANCELLED · 3 Jul 2025 View ↗ PDF 21146-223 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT J Drawing · 3 Jul 2025 View ↗ PDF 21146-220 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT H AND I Drawing · 3 Jul 2025 View ↗ PDF 21146-218 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT G Drawing · 3 Jul 2025 View ↗ PDF 21146-216 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT F CANCELLED · 3 Jul 2025 View ↗ PDF 21146-214 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT E Drawing · 3 Jul 2025 View ↗ PDF 21146-212 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT D. Drawing · 3 Jul 2025 View ↗ PDF 21146-210 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT C Drawing · 3 Jul 2025 View ↗ PDF 21146-208 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT B (SHEET 2 OF 2) Drawing · 3 Jul 2025 View ↗ PDF 21146-207 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT B (SHEET 1 OF 2 Drawing · 3 Jul 2025 View ↗ PDF 21146-206 REV P1 COND 8 - DRAINAGE DESIGN FOR SUB-CATCHMENT A Drawing · 3 Jul 2025 View ↗ PDF 21146-201 REV P1 COND 8 - DRAINAGE DESIGN FOR CATCHMENT 2 Drawing · 3 Jul 2025 View ↗ PDF 21146-200 REV P1 COND 8 - DRAINAGE DESIGN FOR CATCHMENT 1 CANCELLED · 3 Jul 2025 View ↗ PDF COND 8 - CATCHMENT 1 - SW CALCULATION PACK BNG Metric · 3 Jul 2025 View ↗

Plans & drawings 34

PDF 25133.102 A LANDSCAPE PHASING PLAN Drawing · 15 Dec 2025 View ↗ PDF 5099-C5-220 COND 5 - LIGHTING PLAN Drawing · 13 Nov 2025 View ↗ PDF 5099-C5-221 COND 5 -LIGHTING PLAN - SHEET 1 Drawing · 13 Nov 2025 View ↗ PDF 5099-C5-222 COND 5 -LIGHTING PLAN - SHEET 2 Drawing · 13 Nov 2025 View ↗ PDF 5099-C5-210A COND 5 -ACCESS AND PARKING MATERIALS PLAN Drawing · 13 Nov 2025 View ↗ PDF 21146-226 REV P2 COND 9 - CONSTRUCTION PHASE PLAN (SHEET 1 OF 2) Drawing · 4 Nov 2025 View ↗ PDF 5099-C5-210 CONDITION 5 ACCESS & PARKING MATERIALS PLAN CANCELLED · 18 Sept 2025 View ↗ PDF 5099-211 C COND 11 - PROPOSED PHASING PLAN Drawing · 18 Sept 2025 View ↗ PDF 5099-230 B COND 11 - PROPOSED SITE SECTIONS Drawing · 18 Sept 2025 View ↗ PDF 25133.102 COND 16 - 25133.102 LANDSCAPE PHASING PLAN CANCELLED · 18 Sept 2025 View ↗ PDF 25133.103 COND 16 - BOUNDARY TREATMENTS PLAN Drawing · 18 Sept 2025 View ↗ PDF 5099-230 COND 11 - PROPOSED SITE SECTIONS CANCELLED · 3 Jul 2025 View ↗ PDF 5099-211A COND 11 - PROPOSED PHASING PLAN CANCELLED · 3 Jul 2025 View ↗ PDF 5099-210B COND 11 - PROPOSED SITE PLAN Drawing · 3 Jul 2025 View ↗ PDF 5099-130 COND 11 - EXISTING SITE SECTIONS Drawing · 3 Jul 2025 View ↗ PDF 25133.101 A COND 16 - LANDSCAPE PROPOSALS Drawing · 3 Jul 2025 View ↗ PDF 21146-227 REV P1 COND 9 - CONSTRUCTION PHASE PLAN (SHEET 2 OF 2) Drawing · 3 Jul 2025 View ↗ PDF 21146-204 REV P1 COND 8 - STANDARD CONSTRUCTION DETAILS (1 OF 2) Drawing · 3 Jul 2025 View ↗ PDF 21146-205 REV P1 COND 8 - STANDARD CONSTRUCTION DETAILS (2 OF 2) Drawing · 3 Jul 2025 View ↗ PDF 21146-105 REV P1 COND 8 - EXCEEDANCE FLOW PLAN Drawing · 3 Jul 2025 View ↗ PDF 21146-104 REV P1 COND 8 - EXCEEDANCE FLOW PLAN Drawing · 3 Jul 2025 View ↗ PDF 21146-222 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT I Drawing · 3 Jul 2025 View ↗ PDF 21146-221 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT H Drawing · 3 Jul 2025 View ↗ PDF 21146-219 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT G Drawing · 3 Jul 2025 View ↗ PDF 21146-217 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT F Drawing · 3 Jul 2025 View ↗ PDF 21146-215 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT E Drawing · 3 Jul 2025 View ↗ PDF 21146-213 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT D Drawing · 3 Jul 2025 View ↗ PDF 21146-211 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT C Drawing · 3 Jul 2025 View ↗ PDF 21146-209 REV P1 COND 8 - TYPICAL FOREBAY DISCHARGE DETAIL FOR SUB-CATCHMENT B Drawing · 3 Jul 2025 View ↗ PDF 21146-202 REV P1 COND 8 - CATCHMENT 1 CONSTRUCTION DETAILS Drawing · 3 Jul 2025 View ↗ PDF 21146-203 REV P1 COND 8 - CATCHMENT 2 CONSTRUCTION DETAILS Drawing · 3 Jul 2025 View ↗ PDF 21146-224 REV P1 COND 8 - TYPICAL STANDARD SWALE CROSS SECTION DETAILS Drawing · 3 Jul 2025 View ↗ PDF 21146-225 REV P1 COND 8 - TYPICAL CULVERT DESIGN Drawing · 3 Jul 2025 View ↗ PDF 21146-226 P01 COND 9 - CONSTRUCTION PHASE PLAN (SHEET 1 OF 2) CANCELLED · 3 Jul 2025 View ↗

Other documents 41

PDF EMAIL FROM AGENT CONFIRMING CLADDING MIX Correspondence · 19 Dec 2025 View ↗ PDF AGREEMENT TO EOT - 31/12/25 Agreement to extension of time · 19 Dec 2025 View ↗ PDF EMAIL TO AGENT WITH QUERIES Correspondence · 15 Dec 2025 View ↗ PDF EMAIL FROM AGENT WITH REVISED DETAILS Correspondence · 15 Dec 2025 View ↗ PDF ISSUE FIVE COND 5 - SCHEDULE OF DETAILS Other · 27 Nov 2025 View ↗ PDF ISSUE FIVE COND 3 - SCHEDULE OF MATERIALS Other · 27 Nov 2025 View ↗ PDF EMAIL FROM AGENT WITH REVISED SCHEDULES Correspondence · 27 Nov 2025 View ↗ PDF AGREEMENT TO EOT - 5/12/25 Agreement to extension of time · 14 Nov 2025 View ↗ PDF CANEXEL CLADDING BROCHURE Other · 13 Nov 2025 View ↗ PDF COND 3 - BALUSTRADE AND GLASS OPTIONS Other · 13 Nov 2025 View ↗ PDF EMAIL FROM AGENT CONFIRMING MATERIALS COLOUR Correspondence · 13 Nov 2025 View ↗ PDF COND 5 - CRIMPLESHAM GRAVEL DETAILS Other · 13 Nov 2025 View ↗ PDF COND 5- SELF BINDING GRAVEL DETAILS Other · 13 Nov 2025 View ↗ PDF COND 8 - CATCHMENT 1 - SW CALCULATION PACK Other · 4 Nov 2025 View ↗ PDF EMAIL FROM AGENT WITH FURTHER DETAILS Correspondence · 4 Nov 2025 View ↗ PDF EMAIL FROM AGENT WITH FURTHER INFORMATION AND AGREEMENT TO EOT - 14/11/25 Agreement to extension of time · 14 Oct 2025 View ↗ PDF UPDATE AND QUERIES TO AGENT Correspondence · 9 Oct 2025 View ↗ PDF COND 3 - SCHEDULE OF MATERIALS - ISSUE FOUR CANCELLED · 18 Sept 2025 View ↗ PDF COND 5 - SCHEDULE OF DETAILS - ISSUE FOUR CANCELLED · 18 Sept 2025 View ↗ PDF COVERING LETTER FROM AGENT Other · 18 Sept 2025 View ↗ PDF AGREEMENT TO EOT - 10/10/25 Agreement to extension of time · 29 Aug 2025 View ↗ PDF EMAIL TO AGENT WITH QUERY Correspondence · 22 Aug 2025 View ↗ PDF CORRESPONDENCE BETWEEN AGENT, ENGINEER AND THE LLFA Correspondence · 14 Aug 2025 View ↗ PDF COND 3 - SCHEDULE OF MATERIALS - ISSUE TWO CANCELLED · 3 Jul 2025 View ↗ PDF COND 5 - SCHEDULE OF DETAILS - ISSUE TWO CANCELLED · 3 Jul 2025 View ↗ PDF COND 8 - DEFRA STANDARDS CHECKLIST Report · 3 Jul 2025 View ↗ PDF COND 8 - GROUND INVESTIGATION REPORT Report · 3 Jul 2025 View ↗ PDF COND 8 - MAINTENANCE SCHEDULE Other · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT J - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT H - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT I - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT G - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT F - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT E - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT D - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT C - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT B - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - SUB-CATCHMENT A - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - CATCHMENT 2 - SW CALCULATION PACK Report · 3 Jul 2025 View ↗ PDF COND 8 - FOREBAY DESIGN CALCULATION Report · 3 Jul 2025 View ↗ PDF Schedule of Conditions Schedule of Conditions · 3 Jul 2025 View ↗

All documents on the council site ↗

Associated applications 4

  • Part of

    FullApprovedcouncil archive

    Conditions varied

Site constraints 4

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
National infrastructure project 167 m away: Fens Reservoir, at pre-application.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Fenland - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Fenland
Application type
Discharge of condition
Postcode
PE15 0PE
Received
30 Jun 2025
Validated
3 Jul 2025
Ward
Doddington And Wimblington
Parish
Wimblington Parish Council
Case officer
Show
Target decision
5 Dec 2025
Decision
Approve
Decision date
23 Dec 2025
Decision level
Delegated Decision
Applicant
Show
Agent
Avison Young

How this decision compares

Decided in 173 days from validation, 120 days slower than Fenland's median of 53 for discharge of conditions. Approved, as 93% of discharge of conditions here are.

64%decided within 8 weeks
93%approved
221decided in the last year

Plota live figures for discharge of conditions decided by Fenland in the last twelve months, from validation. Fenland decision record →

Public comments

No public comments yet.

Last counted 15 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14101567
Planning Portal ref
PP-14101567
Consultation
26 Nov 2025
Comments by
6 Dec 2025
Statutory expiry
28 Aug 2025
Env. assessment
No
Fenland
Planning Authority Score
6.1/10
Average
#98 of 296 overall
Relevant to this application:
Householder decisions

Fenland is faster than most councils at deciding householder applications: #58 of 296 on speed. Householder applications are slightly more likely to be approved here (93%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Fenland decision statistics
Based on MHCLG data, the year to March 2026
87%
Overall approval rate
Above avg (87%) #170 of 296
93%
Householder approved
Above avg (90%) #128 of 296
77%
Decided in 8 weeks
Above avg (63%) #58 of 296
42%
Extended time limit
Above avg (41%) #163 of 296
78%
Minor dwellings approved
194 decided (1-9 homes)
77%
Major dwellings approved
26 decided (10+ homes)
90%
Change of use approved
29 decided
604
Total decisions
79 refused in the year to March 2026