Flat 513 Lexington Building, Bow Quarter, 60 Fairfield Road, London, E3 2UF Data via plota.co.uk

PA/25/02007/NC - Full Planning Permission Approved

Proposal

Proposed replacement external glazing, replacement of existing rooflight and new rooflight and new air source heat pump located on balcony. Internal alterations to include, removal of the short wall between the kitchen and the living room, enlargement of the tiled floor area in the kitchen, under floor heating to the lower level, thermal upgrades of the existing external walls, new staircase, extension of the existing mezzanine to create additional floor space and other minor associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 27 Nov 2025
✓
Consultation
12 Dec 2025
✓
Approved
21 Jan 2026

Approved on 21 Jan 2026 · Delegated · Last checked 18 Oct 2026

Site constraints 8

Grade II listed: Fairfield Match Works (Bryant and May)
List entry 1065187 · The pin is inside its outline · 7 more listed buildings within 150 m (7 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 7 with distances
Historic England ↗
Fairfield Road conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Archaeological priority area: Tower Hamlets APA 2.20
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 367 m away: Thames Tideway Tunnel
The site is 367 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Inside the Tower Hamlets built-up area; Public transport access: PTAL 3 (moderate), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area86 m² (926 sq ft)
Energy ratingE (50 out of 100), could reach D
PropertyEnd-terrace flat, 3 habitable rooms
Built1991 to 1995
HeatingRoom heaters, electric
WallsSystem built, as built, insulated (assumed)

From the energy performance certificate lodged in March 2023, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
E3 2UF
Received
around 27 Nov 2025
Validated
27 Nov 2025
Ward
Bow East
Case officer
Show
Target decision
22 Jan 2026
Decision
Permit
Decision date
21 Jan 2026
Decision level
Delegated
Applicant
Show
Agent
PLANSTUDIO ARCHITECTURE

How this decision compares

Decided in 55 days from validation, about the council's usual 56 days. Approved, as 85% of full applications here are.

60%decided within 8 weeks
85%approved
557decided in the last year

Plota live figures for full applications decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Comments by
2 Jan 2026
Site or press notice
12 Dec 2025
Statutory expiry
22 Jan 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.