A120 Junction Bentley Road Little Bentley Essex CO7 8SS Data via plota.co.uk

26/00975/EIASCR - EIA Screening Opinion Decided

Proposal

EIA Screening Opinion for extension of merge taper off the A120 junction; construction of a new private access road south of Little Bromley and widening of existing carriageway along Bentley Road and Ardleigh Road; construction of three temporary compounds; and construction of three new bellmouths (JC-B070, JC-B071 and JC-B072). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
26 Jun 2026
✓
Application Closed
16 Jul 2026

Application Closed on 16 Jul 2026 · Delegated Decision · Last checked 17 Jul 2026

Site constraints 2

Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project about 31 m away: North Falls Offshore Wind Farm
The site is about 31 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Norwich to Tilbury (examination closed, recommendation due, about 32 m); Five Estuaries Offshore Wind Farm (decided, about 33 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tendring - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Tendring
Application type
EIA Screening Opinion
Postcode
CO7 8SS
Received
26 Jun 2026
Validated
26 Jun 2026
Ward
The Bentleys & Frating
Parish
Little Bentley Parish Council
Case officer
Show
Target decision
17 Jul 2026
Decision
Application Closed
Decision date
16 Jul 2026
Decision level
Delegated Decision
Applicant
Show

Consultation & key dates

Statutory expiry
17 Jul 2026
Env. assessment
No
Tendring
Planning Authority Score
6.8/10
Good
#70 of 296 councils
Relevant to this application:
Householder decisions

Tendring is faster than most councils at deciding householder applications, ranking #40 out of 296. Only 26% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly less likely to be approved here (89%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tendring decision statistics
Based on MHCLG data, the year to March 2026
85%
Overall approval rate
Below avg (87%) #212 of 296
89%
Householder approved
Below avg (90%) #211 of 296
80%
Decided in 8 weeks
Above avg (63%) #40 of 296
26%
Extended time limit
Below avg (41%) #38 of 296
71%
Minor dwellings approved
114 decided (1-9 homes)
88%
Major dwellings approved
16 decided (10+ homes)
80%
Change of use approved
49 decided
837
Total decisions
127 refused in the year to March 2026