High Marnham Power Station, Power Station Access Fledborough Road, High Marnham, NG22 0FX Data via plota.co.uk

WL/2025/01110 - Local Authority Consultation Determined

Proposal

Local authority consultation: - Screening Opinion for a 400kV Substation Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
6 Nov 2025
Decision
Target date was 20 Nov 2025

Under consideration

No decision has been issued yet. Plota predicted a decision around 23 Nov 2026; it is now day 382.

The consultation period closed on 1 Dec 2025.

Site constraints 3

National infrastructure project: One Earth Solar Farm
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: North Humber to High Marnham (at pre-application, the site is inside its boundary); H2East Pipeline: Humber to Nottinghamshire (at pre-application, the site is inside its boundary).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the High Marnham built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in West Lindsey - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Local Authority Consultation
Postcode
NG22 0FX
Received
6 Nov 2025
Validated
6 Nov 2025
Case officer
Show
Target decision
20 Nov 2025
Decision level
Delegated
Applicant
Show

Decision outlook

Day 382, past the statutory target. 83% of other in West Lindsey are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 9 Oct 2026.

Day 382326 days past the 56-day target
65%decided within 8 weeks
95%approved
2,220decided in the last year

Plota live figures for other decided across the UK in the last twelve months, from validation; too few recent other in West Lindsey to go on. West Lindsey decision record →

Consultation & key dates

Alt. reference
EC/2025/01166
Comments by
1 Dec 2025
Committee
10 Nov 2025
Statutory expiry
20 Nov 2025
Env. assessment
No
West Lindsey
Planning Authority Score
5.3/10
Average
#134 of 296 overall
Relevant to this application:
Householder decisions

West Lindsey is #110 of 296 councils on householder decision speed. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
West Lindsey decision statistics
Based on MHCLG data, the year to March 2026
93%
Overall approval rate
Above avg (87%) #70 of 296
94%
Householder approved
Above avg (90%) #123 of 296
72%
Decided in 8 weeks
Above avg (63%) #110 of 296
44%
Extended time limit
Above avg (41%) #187 of 296
88%
Minor dwellings approved
80 decided (1-9 homes)
100%
Major dwellings approved
25 decided (10+ homes)
94%
Change of use approved
33 decided
562
Total decisions
39 refused in the year to March 2026