89 Purewell Christchurch BH23 1EJ Data via plota.co.uk

P/26/04790/CLP - Certificate of Lawfulness for proposed use or development Application Under Consideration

Proposal

Lawful Development Certificate for proposed rear single storey extension . Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
5 Oct 2026
✓
Validated
29 Oct 2026
Decision
Expected by 24 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision around 23 Dec 2026, from BCP's recent extensions.

Site constraints 9

Purewell conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Article 4 direction
Hovercraft in the Solent. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From rivers and the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Local nature reserve 253 m away: Purewell Meadows
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
National infrastructure project 894 m away: Navitus Bay Wind Park
The site is 894 m from the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
4 listed buildings within 150 m; SSSI 297 m away: Purewell Meadows SSSI; Inside the Christchurch (Bournemouth, Christchurch and Poole) built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 3

Last sold for £450,000 in May 2024. Semi-detached house, freehold.

22 May 2024£450,000
26 May 2000£144,950
16 September 1998£89,950

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area118 m² (1,270 sq ft)
Energy ratingD (56 out of 100), could reach C
PropertySemi-detached house, 6 habitable rooms
BuiltBefore 1900
HeatingBoiler and radiators, mains gas
WallsSolid brick, as built, no insulation (assumed)

From the energy performance certificate lodged in August 2023, the latest held for this property, matched to this application by its address. The building may have changed since. View the certificate

Work with planning data?

Every application in BCP - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
BCP
Application type
Certificate of Lawfulness for proposed use or development
Postcode
BH23 1EJ
Received
5 Oct 2026
Validated
29 Oct 2026
Ward
Christchurch Town
Parish
Christchurch Town Council
Case officer
Show
Decision level
Delegated
Applicant
Show
Agent
Darryl Howells Planning Consultancy

Decision outlook

Day 20 of the 56-day target. BCP usually decides extensions by day 55.

Day 2036 days to the 56-day target
72%decided within 8 weeks
84%approved
1,121decided in the last year

Plota live figures for extensions decided by BCP in the last twelve months, from validation. BCP decision record →

BCP
Planning Authority Score
1.7/10
Poor
#279 of 296 councils
Relevant to this application:
Householder decisions

BCP is slower than most councils at deciding householder applications, ranking #256 out of 296. The council extends the time limit on 60% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly less likely to be approved here (88%) than the national average (90%).

Frequently extends decision deadlines
expect longer than the statutory limit
These figures are council-wide context, not a prediction for this application. View full council performance
BCP decision statistics
Based on MHCLG data, the year to March 2026
83%
Overall approval rate
Below avg (87%) #233 of 296
88%
Householder approved
Below avg (90%) #214 of 296
44%
Decided in 8 weeks
Below avg (63%) #256 of 296
60%
Extended time limit
Above avg (41%) #267 of 296
67%
Minor dwellings approved
346 decided (1-9 homes)
68%
Major dwellings approved
56 decided (10+ homes)
81%
Change of use approved
78 decided
2,244
Total decisions
392 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.