Substation Coll Back Isle Of Lewis Data via plota.co.uk

26/00392/PPD - Planning Permission (Detailed) Awaiting decision

Proposal

Erect switchroom and transformer building; install 33kV & 11kV transformers; form new access road; associated ancillary works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
2 Oct 2026
✓
Validated
21 Oct 2026
✓
Consultation
22 Oct 2026
Decision
Expected by 20 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision by 22 Dec 2026, from Western Isles's recent utility and infrastructure works.

The consultation period closed on 12 Nov 2026.

Important details

Application type
Planning Permission (Detailed)
Received
2 Oct 2026
Validated
21 Oct 2026
Ward
Loch A Tuath
Parish
Back
Case officer
Show
Target decision
20 Dec 2026
Decision level
Delegate Decision
Applicant
Show
Agent
Dalcour Maclaren

Decision outlook

Day 33 of the 56-day target. Western Isles usually decides utility and infrastructure works by day 39.

Day 3323 days to the 56-day target
59%decided within 8 weeks
100%approved
52decided in the last year

Plota live figures for utility and infrastructure works decided by Western Isles in the last twelve months, from validation. Western Isles decision record →

Public comments

No public comments yet.

Last counted 20 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
100770770-001
Consultation
22 Oct 2026
Comments by
12 Nov 2026
Site or press notice
29 Oct 2026
Statutory expiry
20 Dec 2026
Env. assessment
No