Hard-rock quarry extension at Land At Rosarie Quarry, Keith

Summary of planning committee decision

Decided by Moray Planning and Regulatory Services Committee on 2 Jul 2026.

25/01116/APPApproved

What was proposed

The application sought partly retrospective consent and new permission for a hard-rock quarry extension, processing area, access, ecological buffer and related infrastructure.

“A major planning application (incorporating Environmental Impact Assessment EIA) which seeks partly retrospective consent to extend a hard- rock quarry and for associated infrastructure on land at Rosarie Quarry, Keith. • The retrospective elements of the proposal include: • construction of an agricultural road, • initial hard rock mineral extraction and mineral processing, • the construction of a temporary junction.”

“The hard rock would be processed on site into stone and stone based products (including lime-rich products for use on farmland) to service the existing local market. • The proposed extractive area of the site is approximately 15hectares. • The quarry will have a maximum depth of approximately 32m and the quarry floor is anticipated to be around 115 above sea level. • The extraction works are to be phased into two phases: • Phase 1 - Eastern void – approx.”

Officer report

The site and its history

The site covers about 18.4 hectares beside the A96 and includes a previous quarry, agricultural fields, a burn and nearby woodland.

“The application site is approximately 18.4 hectares of land in total, and this includes the area of a previously approved quarry (19/00291/MIN refers). • The proposed extractive area is approximately 15 hectares. • The remainder of the site is formed of three existing agricultural fields (not considered Prime Agricultural Land). • An unnamed burn forms a valley through the centre of the site which separates the eastern and western voids.”

“The site areas are not subject to any international, national, regional or local landscape, built environment or nature conservation designations. The Mill Wood Site of Special Scientific Interest (SSSI) lies approx. 6km to the east of the site. • The site lies within an area identified to be at high risk of surface water flooding on the SEPA maps.”

Officer report

Earlier applications and consultation

Earlier permissions, screening and consultation processes preceded the application, including a 2019 quarry permission that was not lawfully implemented.

“23/02233/PAN – Proposal of Application Notice relating to current proposal. Reported to Committee on 15 February 2024. Members requested that mitigating factors to address the increase in traffic volume onto the A95 as a result of the development be considered. A Public event was undertaken on 28 March 2024 at Longmore Community Hall in Keith under 23/02233/PAN.”

“19/00921/MIN – Proposal to develop a hard rock quarry, mineral processing area and formation of screening bunds (site area of approx. 1.7ha) at Rosarie. Planning permission granted subject to conditions on 19 December 2019. Quarry was in operation during summer of 2023 however the permission was not lawfully implemented as not all suspensive conditions has been discharged and works ceased.”

Officer report

What consultees said

Planning, environmental, transport, water, forestry, railway and access consultees raised no objections after additional information, subject to conditions and advice.

“Private Water Supplies – No Objections following submission of additional information relating to the water source for drilling and processing, dust suppression and welfare (potable supply), turbidity testing of Loan Burn and submission of a Detailed Water Management Plan.”

“Transport Scotland – No Objections subject to a condition requiring that the access onto the A95(T) road is provided prior to commencement and operation of the development. Transport Scotland satisfied that detail around the access, such as visibility splays are adequately detailed on the submitted plans.”

Officer report

The committee’s decision

The committee unanimously granted planning permission, with conditions controlling the consent period, operating hours, noise, blasting, access, water, restoration and biodiversity.

“Following consideration, the Committee unanimously agreed to grant planning permission in respect of Planning Application 25/01116/APP subject to the following conditions and reasons:”

Minutes

The members' reasons

“The Committee noted that the application had been referred to Committee as it is a major planning application for the extraction of Minerals where the site area exceeds 2 ha.”

Minutes

Approved subject to 4 conditions, set out in the minutes.

Source: the council's minutes, quoted word for word.

Councillors at the meeting

Apologies Theresa Ann Coull SNP, Jérémie Fernandes SNP, Marc Macrae Conservative

Source: Plota analysis of the council's minutes; parties from Democracy Club.

Sources

  • Moray Planning and Regulatory Services Committee minutes, 2 July 2026
  • Agenda and papers (council website)

Source: Plota analysis of Moray's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Moray
Date
Thursday 2 July 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Vote
Unanimous
Councillors
11Conservative 5Labour 2SNP 2Independent 11 otherShow councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

8 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →