Land At Prince Of Wales Open Space And Turkey Brook Ordnance Road Enfield EN3 Data via plota.co.uk

26/04036/FUL - Full Application in Progress

Proposal

Enlargement of the existing bellmouth and access off Mollison Avenue (A1055); and revision to the route alignment of the temporary haul road from Mollison Avenue (A1055) to Brimsdown Substation on the land between Mollison Avenue and the Prince of Wales Open Space, to facilitate the National Grid (North London Reinforcement Project (NLRP). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Sept 2026
✓
Validated
2 Oct 2026
✓
Consultation
2 Oct 2026
Decision
Expected by 1 Jan 2027

This application is under consideration - no decision has been issued yet. Plota predicts a decision around 21 Nov 2026, from Enfield's recent utility and infrastructure works. Comments are open until 4 Nov 2026.

Comment on this application ↗

Documents 33

Statements & assessments 26

PDF HERITAGE STATEMENT Heritage Statement · 2 Oct 2026 View ↗ PDF Noise impact assessment - Redacted 25-09-2026 Noise Impact Assessment · 25 Sept 2026 View ↗ PDF ARBORICULTURAL STATEMENT AND TREE ASSESSMENT Tree Survey · 22 Sept 2026 View ↗ PDF STAGE 1 WATER FRAMEWORK DIRECTIVE ASSESSMENT Environmental Statement · 22 Sept 2026 View ↗ PDF Planning statement Planning Statement · 22 Sept 2026 View ↗ PDF FLOOD RISK ASSESSMENT - PART 1 Flood Risk Assessment · 22 Sept 2026 View ↗ PDF FLOOD RISK ASSESSMENT - PART 4 Flood Risk Assessment · 22 Sept 2026 View ↗ PDF FLOOD RISK ASSESSMENT - PART 3 Flood Risk Assessment · 22 Sept 2026 View ↗ PDF FLOOD RISK ASSESSMENT - PART 2 Flood Risk Assessment · 22 Sept 2026 View ↗ PDF FLOOD RISK ASSESSMENT - PART 6 Flood Risk Assessment · 22 Sept 2026 View ↗ PDF FLOOD RISK ASSESSMENT - PART 5 Flood Risk Assessment · 22 Sept 2026 View ↗ PDF CONSTRUCTION TRAFFIC MANAGEMENT PLAN - PART 1 Transport Assessment · 22 Sept 2026 View ↗ PDF Air quality assessment Air Quality Assessment · 22 Sept 2026 View ↗ PDF TRANSPORT STATEMENT Transport Assessment · 22 Sept 2026 View ↗ PDF CONSTRUCTION TRAFFIC MANAGEMENT PLAN - PART 2 Transport Assessment · 22 Sept 2026 View ↗ PDF LAND CONTAMINATION ASSESSMENT PART 1 Land Contamination Assessment · 22 Sept 2026 View ↗ PDF LAND CONTAMINATION ASSESSMENT PART 3 Land Contamination Assessment · 22 Sept 2026 View ↗ PDF LAND CONTAMINATION ASSESSMENT PART 2 Land Contamination Assessment · 22 Sept 2026 View ↗ PDF LAND CONTAMINATION ASSESSMENT PART 4 Land Contamination Assessment · 22 Sept 2026 View ↗ PDF LAND CONTAMINATION ASSESSMENT PART 5 Land Contamination Assessment · 22 Sept 2026 View ↗ PDF LAND CONTAMINATION ASSESSMENT PART 6 Land Contamination Assessment · 22 Sept 2026 View ↗ PDF BIODIVERSITY NET GAIN DESIGN STAGE REPORT Biodiversity Statement · 22 Sept 2026 View ↗ PDF BNG METRIC CALCULATION Biodiversity Metric Calculation Tool · 22 Sept 2026 View ↗ PDF HABITAT REGULATIONS ASSESSMENT Habitat Management and Monitoring Plan · 22 Sept 2026 View ↗ PDF ECOLOGICAL IMPACT ASSESSMENT PART 2 Supporting Information · 22 Sept 2026 View ↗ PDF ECOLOGICAL IMPACT ASSESSMENT PART 1 Supporting Information · 22 Sept 2026 View ↗

All documents on the council site ↗

Site constraints 4

Article 4 direction
Borough wide. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Air quality management area: Enfield AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Inside the Enfield built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 3 October 2026. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Enfield - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Enfield
Application type
Full
Postcode
EN3 6JJ
Received
22 Sept 2026
Validated
2 Oct 2026
Ward
Enfield Lock
Case officer
Show
Target decision
1 Jan 2027
Decision level
Delegated Decision
Agent
Arup

Decision outlook

Day 2 of the 56-day target. Enfield usually decides utility and infrastructure works by day 50.

Day 254 days to the 56-day target
83%decided within 8 weeks
88%approved
59decided in the last year

Plota live figures for utility and infrastructure works decided by Enfield in the last twelve months, from validation. Enfield decision record →

Public comments

No public comments yet.

Last counted 3 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15048927
Consultation
2 Oct 2026
Comments by
4 Nov 2026
Site or press notice
21 Oct 2026
Statutory expiry
1 Jan 2027
Env. assessment
No
Enfield
Planning Authority Score
6.9/10
Good
#65 of 296 councils
Relevant to this application:
Householder decisions

Enfield is one of the fastest councils in England for householder decisions, ranking #15 out of 296. Only 5% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Enfield is also one of the strictest councils - it refuses more householder applications than almost any other, with only 83% approved vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Enfield decision statistics
Based on MHCLG data, the year to March 2026
78%
Overall approval rate
Below avg (87%) #271 of 296
83%
Householder approved
Below avg (90%) #260 of 296
90%
Decided in 8 weeks
Above avg (63%) #15 of 296
5%
Extended time limit
Below avg (41%) #1 of 296
60%
Minor dwellings approved
265 decided (1-9 homes)
63%
Major dwellings approved
8 decided (10+ homes)
72%
Change of use approved
322 decided
1,939
Total decisions
433 refused in the year to March 2026