Hinkley Point B Power Station TA5 1UD Data via plota.co.uk

SCC/4137/2025/SCR Decided

Proposal

Environmental Impact Assessment (EIA) screening opinion in connection with the construction and operation of a Decommissioning Waste Processing Facility at Hinkley Point B Power Station site. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Nov 2025
✓
Screening/Scoping Opinion Decision Issued
19 Dec 2025

Screening/Scoping Opinion Decision Issued on 19 Dec 2025 · Last checked 26 Oct 2026

Site constraints 7

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
National infrastructure project about 55 m away: Hinkley Point C Connection
The site is about 55 m from the project boundary. Electricity line, decided. The project page says whether consent was granted. Also within 2 km: Hinkley Point C New Nuclear Power Station (decided, about 79 m); Hinkley Point C Connection Project Material Change (at pre-application, about 58 m); Hinkley Point C New Nuclear Power Station Material Change 1 (at pre-application, about 572 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Special area of conservation about 183 m away: Severn Estuary (England)
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
SSSI about 184 m away: Bridgwater Bay SSSI
Natural England may need consulting, depending on what is proposed.
Sites of special scientific interest are the best wildlife and geological sites in the country. Development likely to harm one is rarely permitted.
Also on the record
Inside the Shurton built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 1 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Somerset - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Somerset
Postcode
TA5 1UD
Validated
28 Nov 2025
Decision
Screening/Scoping Opinion Decision Issued
Decision date
19 Dec 2025
Applicant
Show
Agent
Laura Cherry
Somerset
Planning Authority Score
6.1/10
Average
#100 of 296 overall
Relevant to this application:
Householder decisions

Somerset is faster than most councils at deciding householder applications: #88 of 296 on speed. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Somerset decision statistics
Based on MHCLG data, the year to March 2026
88%
Overall approval rate
Above avg (87%) #161 of 296
94%
Householder approved
Above avg (90%) #117 of 296
74%
Decided in 8 weeks
Above avg (63%) #88 of 296
39%
Extended time limit
Below avg (41%) #143 of 296
78%
Minor dwellings approved
699 decided (1-9 homes)
92%
Major dwellings approved
77 decided (10+ homes)
89%
Change of use approved
158 decided
3,740
Total decisions
438 refused in the year to March 2026