The Cliff House, Marine Drive West, Barton-on-Sea, New Milton BH25 7QL Data via plota.co.uk

26/11064 - Full Planning Permission Registered

Proposal

Temporary erection of a marquee for up to 9 weeks per year (including erection and removal), for a period of 3 years Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
11 Nov 2026
✓
Validated
12 Nov 2026
✓
Consultation
13 Nov 2026
Decision
Expected by 7 Jan 2027

Under consideration

No decision has been issued yet. Plota predicts a decision around 4 Jan 2027, from New Forest (District)'s recent full applications.

Comments are open until 11 Dec 2026

Comment on this application ↗

Site constraints 8

Green belt: South West Hampshire
Inappropriate development needs very special circumstances.
Green belt policy allows a short list of exceptions, such as limited extensions and replacement buildings. Anything else needs very special circumstances that clearly outweigh the harm. Some green belt land can count as grey belt, where it does not strongly serve the green belt's purposes. The council decides this in its green belt assessment or on each application, so we do not mark it here.
Read the government guidance ↗
Article 4 direction
Hovercraft in the Solent. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project: Navitus Bay Wind Park
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Special protection area 177 m away: Solent and Dorset Coast
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
SSSI 48 m away: Highcliffe to Milford Cliffs SSSI
Natural England may need consulting, depending on what is proposed.
Sites of special scientific interest are the best wildlife and geological sites in the country. Development likely to harm one is rarely permitted.
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Inside the Barton on Sea built-up area; Priority habitat 24 m away: No main habitat but additional habitats present.
Not affected
Outside flood zones 2 and 3 · No listed building at the site · No scheduled monument at the site

Checked on 14 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area501 m² (5,393 sq ft)
Energy ratingD (asset rating 94)
UseC1 Hotels
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in September 2013, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in New Forest (District) - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
BH25 7QL
Received
11 Nov 2026
Validated
12 Nov 2026
Ward
Barton & Becton
Parish
New Milton
Case officer
Show
Target decision
7 Jan 2027
Applicant
Show
Agent
Edward Heron MRICS Limited

Decision outlook

Day 11 of the 56-day target. New Forest (District) usually decides full applications by day 53.

Day 1145 days to the 56-day target
66%decided within 8 weeks
92%approved
746decided in the last year

Plota live figures for full applications decided by New Forest (District) in the last twelve months, from validation. New Forest (District) decision record →

Public comments

24comments received
1 neutral23 supporting

96% support · above the UK average of 16%

22 neighbours consulted · Last counted 21 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15313177
Planning Portal ref
PP-15313177
Consultation
13 Nov 2026
Comments by
11 Dec 2026
Env. assessment
No
New Forest (District)
Planning Authority Score
7.8/10
Good
#29 of 296 overall
Relevant to this application:
Householder decisions

New Forest (District) is faster than most councils at deciding householder applications: #37 of 296 on speed. Householder applications are slightly more likely to be approved here (96%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
New Forest (District) decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #112 of 296
96%
Householder approved
Above avg (90%) #54 of 296
80%
Decided in 8 weeks
Above avg (63%) #37 of 296
35%
Extended time limit
Below avg (41%) #103 of 296
69%
Minor dwellings approved
87 decided (1-9 homes)
91%
Major dwellings approved
11 decided (10+ homes)
78%
Change of use approved
40 decided
885
Total decisions
85 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use