Replacement four-bedroom home at 4 Knowle Hill, Kimberley

Summary of planning committee decision

Decided by Broxtowe Planning Committee on 28 Oct 2026.

26/00495/FULApproved

What was proposed

The application proposed demolishing the existing dwelling, building a replacement four-bedroom detached house and altering the detached garage’s rear dormer.

“The application is brought to the Committee at the request of Councillor A Cooper. 1. Purpose of the Report 1.1 The application seeks planning permission to demolish a dwelling and construct a replacement four-bedroom detached dwelling and alter the rear dormer of the detached garage. 2. Recommendation The Committee is asked to resolve that planning permission be approved for the reasons outlined in the appendix. 3.”

Officer report

The site and its history

The site is a residential property on a steep cul-de-sac, with a garage, garden, neighbouring homes and an access driveway nearby.

“The application site is on Knowle Hill in Kimberley, a built up residential area. Knowle Hill is a steep cul-de-sac rising uphill from north to south. There are a variety of house sizes and styles running along the eastern side of the road with Kimberley Cemetery and allotments on the western side. The application site contains a modest detached property with a detached garage to the rear with a generous garden.”

“15/00426/FUL – Construct single storey rear extension and detached garage 3.2 10/00202/FUL – Construct Dwellinghouse – refused…”

Officer report

What neighbours said

Neighbours objected over daylight, privacy, character, construction effects, access, possible property damage, boundaries and insufficient land-stability information.

“- Object to noise and dust of construction - Demolition – what is the process? What measures will be put in place to protect our property from damage or falling materials and any Plant used? How will materials be removed from site as the access road to the side is not suitable for heavy vehicles as experience during the construction of the double garage? - Objection to Piling if it is to be used for the foundations - The construction of the double garage created problems…”

“- Will the contractor or applicant provide insurance details prior to any approved demolition/ construction? - Had to repair cracks following previous construction of garage - Concerns regarding access alongside driveway/access and use of this access being required at all times by The Coppice - Concerns about the garden boundaries of 4 and 6 Knowle Hill altering - No explanation of why it is necessary to demolish the existing property - Insufficient information regarding…”

Officer report

Who spoke

The applicant and an objector made representations to the committee before the general debate.

What members debated

Members considered the property suitable for renovation and appropriate for the area, but were concerned about land stability and effects on neighbouring areas.

“The Committee considered all the representations presented to it and opened the debate, which covered that the property required renovation and was appropriate for the area. However, concern was raised regarding the stability of the land and how this would affect the neighbouring area. It was therefore proposed that there should be an additional condition in relation to a phase 2 geo-technical investigation and report.”

Minutes

The decision

The committee resolved to grant permission through delegated authority, adding a condition requiring a geo-technical investigation and report before demolition or development.

“RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission subject to:”

“No development, including demolition, shall commence until a geo- technical investigation and report, as recommended in the Phase I Geo- environmental Assessment dated November 2025, has been submitted to and approved in writing by the Local Planning Authority. The report shall include measures to maintain land stability during demolition and construction and recommendations for foundation design.”

Minutes

Conditions added

The permission included controls covering construction management, biodiversity, highway works, privacy glazing, land stability and construction hours.

“A risk assessment of construction activities that may affect biodiversity; • Identification of biodiversity protection zones; • Measures to avoid or minimise impacts on biodiversity during construction, including lighting controls; • Details of the location and timing of sensitive works; • Arrangements for ecological supervision, including when specialist ecologists will be present on site; • Roles, responsibilities and communication procedures for biodiversity management;…”

Minutes

Councillors at the meeting

The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Broxtowe Planning Committee minutes, 28 October 2026
  • Agenda and papers (council website)

Source: Plota analysis of Broxtowe's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Broxtowe
Date
Wednesday 28 October 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
13Broxtowe Alliance 6Conservative 3Labour 2Independent 1Lib Dem 1Show votes
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

33 decisions in the 12 months to this meeting, 13 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →