112 Millmarsh Lane Enfield EN3 7XG Data via plota.co.uk

25/04259/FUL - Full Approved

Proposal

Erection of steel framed mezzanine platform to support new chiller plant, steel access stairs and single storey lean to extension to rear of existing compressor building. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
9 Dec 2025
✓
Validated
29 Dec 2025
✓
Consultation
29 Dec 2025
✓
Approved
20 Feb 2026

Approved on 20 Feb 2026 · Delegated Decision · Last checked 5 Oct 2026

Site constraints 9

Article 4 direction
Borough wide. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Strategic industrial land
Reserved for industry and logistics.
The London Plan protects strategic industrial locations from other uses; release needs a plan-led process.
Archaeological priority area: River valley deposits with high prehistoric and palaeonvironmental potential.
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Enfield AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 409 m away: North London (Electricity Line) Reinforcement
The site is 409 m from the project boundary. Electricity line, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
SSSI 419 m away: Chingford Reservoirs SSSI; Inside the Enfield built-up area; Public transport access: PTAL 1b (very poor), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area16,387 m² (176,388 sq ft)
Energy ratingC (asset rating 52)
UseB2 to B7 General Industrial and Special Industrial Groups
HeatingAir Conditioning

From the energy performance certificate lodged in July 2014, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Enfield - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Enfield
Application type
Full
Postcode
EN3 7XG
Received
9 Dec 2025
Validated
29 Dec 2025
Ward
Brimsdown
Case officer
Show
Target decision
23 Feb 2026
Decision
Granted With Conditions
Decision date
20 Feb 2026
Decision level
Delegated Decision
Applicant
Show
Agent
FRANCIS BRADSHAW CONSULTING

How this decision compares

Decided in 53 days from validation, about the council's usual 55 days. Approved, as 72% of full applications here are.

77%decided within 8 weeks
72%approved
665decided in the last year

Plota live figures for full applications decided by Enfield in the last twelve months, from validation. Enfield decision record →

Public comments

No public comments yet.

11 neighbours consulted · Last counted 5 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14548785
Planning Portal ref
PP-14548785
Neighbours
18 Dec 2025
Consultation
29 Dec 2025
Comments by
27 Jan 2026
Site or press notice
6 Jan 2026
Statutory expiry
23 Feb 2026
Env. assessment
No
Enfield
Planning Authority Score
6.9/10
Good
#65 of 296 councils
Relevant to this application:
Householder decisions

Enfield is one of the fastest councils in England for householder decisions, ranking #15 out of 296. Only 5% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Enfield is also one of the strictest councils - it refuses more householder applications than almost any other, with only 83% approved vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Enfield decision statistics
Based on MHCLG data, the year to March 2026
78%
Overall approval rate
Below avg (87%) #271 of 296
83%
Householder approved
Below avg (90%) #260 of 296
90%
Decided in 8 weeks
Above avg (63%) #15 of 296
5%
Extended time limit
Below avg (41%) #1 of 296
60%
Minor dwellings approved
265 decided (1-9 homes)
63%
Major dwellings approved
8 decided (10+ homes)
72%
Change of use approved
322 decided
1,939
Total decisions
433 refused in the year to March 2026