College campus redevelopment at Coleg Sir Gar Pibwrlwyd Campus, Carmarthen
Summary of planning committee decision
Decided by Carmarthenshire Planning Committee on 12 Mar 2026.
What was proposed
The application proposed demolishing the existing northern campus buildings and creating four new buildings, workshops, parking, access improvements and landscaping for educational use.
“The principal access into the site is to be provided via the existing main entrance into the site from Pibwrlwyd Lane. This access is proposed to be widened to allow for two way traffic and will lead into a large terraced car parking area providing in excess of 240 no. standard car parking spaces and 12 no. accessible bay (inclusive of 12 electrical vehicle charging bays).”
“Within the proposed campus area, the landscaping proposals have developed around the design principle of using ‘Green Fingers’ of vegetation to break up buildings and parking areas. Existing hedgerows along the site’s southern and eastern boundaries are proposed to be retained and supplemented. Additional hedgerow planting, of approximately 200linear meters, proposed along a section of the southern boundary, and entirely along the northern boundary is also proposed.”
Officer report
The site and its setting
The site forms part of an established further education campus beside Pibwrlwyd Lane, with existing buildings, open fields, mature vegetation and a listed farmhouse nearby.
“The site forms part of the established Coleg Sir Gâr Pibwrlwyd Campus, a further education college providing a range of educational courses for school pupils, post-16 further education learners, higher education students and adult learners.”
“The northern campus includes existing college buildings of various ages, ancillary structures, car parking areas and various intervening areas of grassland including a number of mature trees, hedgerows and vegetation. The eastern extent of the campus is delineated by a hedgerow and a line of mature trees, beyond which lines a rural lane which provides access to the surrounding agricultural fields. A drainage ditch is also located along this boundary.”
Officer report
Earlier planning history
The campus has had various earlier permissions and demolition decisions, including applications from 1978 to 2021.
“The application site area has, by reason of its historic use as a college campus, been the subject of various planning permissions in the past which are summarised below.”
“PL/01497 - Demolition of Two Storey, Frame and Cladding 'System' Building Constructed Circa 1960 - Prior Approval Not Required - 17/5/2021”
Officer report
Consultation responses
Most consultees raised no objection or supported the scheme subject to conditions, while the Built Heritage Officer objected to harm to the listed farmhouse setting.
“Landscape Officer – raises no objection to the proposed development, noting that although the scheme represents a large‐scale intervention involving substantial earthworks, changes to site levels and tree loss, the associated visual and landscape effects can be appropriately mitigated.”
“Built Heritage Officer – objects to the development on grounds that the introduction of new built form into the remaining open fields to the north would erode the historic rural setting that contributes to the character and significance of the Grade II* listed Pibwrlwyd Farmhouse, resulting in harmful encroachment that fails to preserve its setting.”
Officer report
Who spoke
A representation objected to the application, and the applicant’s representative and Senior Development Management Officer responded to the issues raised.
Committee discussion
The committee received a presentation and heard the recommendation, an objection and responses to the issues raised.
“Following a presentation by the Senior Development Management Officer, the Committee was advised that the Head of Place and Sustainability was recommending that the Committee be minded to approve the application, subject to conditions and subject to NRW agreeing with the conclusions of the draft Habitats Regulations Assessment, for the reasons detailed within the written report.”
“The applicant’s representative and Senior Development Management Officer responded to the issues raised…”
Minutes
Councillors at the meeting
- William Tyssul EvansChairPlaid Cymru
- John Mansel CharlesPlaid Cymru
- Ken HowellPlaid Cymru
- Bertram Dorian James PhillipsPlaid Cymru
- Cyng. Edward SkinnerLabour
- Cyng. Russell SparksPlaid Cymru
- Cyng. Gareth ThomasPlaid Cymru
- Cyng. Sue AllenIndependent
- Cyng. Terry DaviesPlaid Cymru
- Cyng. John JamesIndependent
- Cyng. Dai NicholasIndependent
- Cyng. Denise OwenPlaid Cymru
- Cyng. Michael ThomasLabour
- Dewi Elwyn WilliamsPlaid Cymru
- Cyng. Stephen WilliamsIndependent
Source: Plota analysis of the council's minutes; parties from the council's list of councillors and Democracy Club.
Sources
- Carmarthenshire Planning Committee minutes, 12 March 2026
- Agenda and papers (council website)
Source: Plota analysis of Carmarthenshire's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Carmarthenshire Planning Committee
- Council
- Carmarthenshire
- Date
- Thursday 12 March 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Councillors
- 15Plaid Cymru 9Independent 2Labour 2Independent 2Show councillors
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Carmarthenshire committee decisions →
This committee's year
32 decisions in the 12 months to this meeting, 6 against officer advice.
Source: Plota analysis of the committee's minutes.