Currys National Distribution Centre Newlink Business Park Long Hollow Way Winthorpe Newark On Trent NG24 2NH Data via plota.co.uk

26/00571/FUL - Full Planning Permission Awaiting decision

Proposal

Construction of Storage Building. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
17 Apr 2026
✓
Consultation
26 May 2026
Decision
Target date was 12 Jun 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 23 Nov 2026; it is now day 220.

Site constraints 3

National infrastructure project 309 m away: A46 Newark Bypass
The site is 309 m from the project boundary. Highway, decided. The project page says whether consent was granted. Also within 2 km: H2East Pipeline: Humber to Nottinghamshire (at pre-application, 1.3 km).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Newark-on-Trent built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Newark and Sherwood - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
NG24 2NH
Received
17 Apr 2026
Validated
17 Apr 2026
Ward
Collingham
Parish
Winthorpe
Case officer
Show
Target decision
12 Jun 2026
Applicant
Show
Agent
WPL Consulting LLP

Decision outlook

Day 220, past the statutory target. 65% of commercial and major works in Newark and Sherwood are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 19 Nov 2026.

Day 220164 days past the 56-day target
43%decided within 8 weeks
100%approved
43decided in the last year

Plota live figures for commercial and major works decided by Newark and Sherwood in the last twelve months, from validation. Newark and Sherwood decision record →

Public comments

No public comments yet.

Last counted 19 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14842420
Planning Portal ref
PP-14842420
Consultation
26 May 2026
Statutory expiry
12 Jun 2026
Env. assessment
No
Newark and Sherwood
Planning Authority Score
3.9/10
Below average
#198 of 296 overall
Relevant to this application:
Householder decisions

Newark and Sherwood is slower than most councils at deciding householder applications: #241 of 296 on speed. 54% of applications have the time limit extended, above the 41% national average. Householder applications are slightly more likely to be approved here (96%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Newark and Sherwood decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #88 of 296
96%
Householder approved
Above avg (90%) #55 of 296
50%
Decided in 8 weeks
Below avg (63%) #241 of 296
54%
Extended time limit
Above avg (41%) #244 of 296
80%
Minor dwellings approved
110 decided (1-9 homes)
88%
Major dwellings approved
25 decided (10+ homes)
82%
Change of use approved
33 decided
767
Total decisions
63 refused in the year to March 2026