Eggborough Power Station Selby Road Eggborough East Yorkshire Data via plota.co.uk

Decided SELZG2025/0805/DOC
Council
Date received
8 Aug 2025
Date validated
8 Aug 2025

Description

Discharge of Condition 11 (Written Scheme of Investigation) of planning application Section 73 application to vary conditions 03 (plans) and 04 (appearance, scale & layout) of approval Section 73 application to vary condition 15 (30 year Biodiversity Enhancement Management and Monitoring Plan), and delete conditions 16 (Ecological Enhancement Measures) and 26 (surface water) of approval Construction and operation of a battery energy storage system with an electrical output capacity of up to 500MW and associated development including substation, control building(s), electrical cabling including below ground 400kV cabling, roadways and modified accesses, site security infrastructure, lighting, boundary treatments and landscaping granted on 17 January 2023 Data via plota.co.uk

Last checked

Associated applications 13

Site constraints 4

National infrastructure project: Eggborough CCGT
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Knottingley Power Project (decided, 1.6 km); East Coast Hydrogen Humber Pipeline (at pre-application, 565 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Coalfield, development low risk area; Inside the Eggborough built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.