Land West Of The Southern End Of Turbine Way, Swaffham, Norfolk Data via plota.co.uk

PL/2026/1402/FMIN - FMIN minor application Pending Consideration

Proposal

Erection of 2 no light industrial building (use Class E(g), B2, B8), subdivided into 4 units for each - Schedule 2 Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
6 Oct 2026
✓
Validated
21 Oct 2026
Decision
Expected by 16 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 23 Dec 2026 and 21 Jan 2027, from Breckland's recent commercial and major works.

Documents 22

Application forms 1

PDF Commenter’s name hidden Show Application Forms/Certificates (public/redacted) · 16 Oct 2026 View ↗

Consultation & comments 2

PDF Commenter’s name hidden Show Public Rights of Way Officer Comments · 12 Nov 2026 View ↗
PDF 1402-27-10-26 Highways Comment Highway Comments · 27 Oct 2026 View ↗

All documents on the council site ↗

Site constraints 2

Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 528 m away: The Droves Solar Farm
The site is 528 m from the project boundary. Generating station, under examination. Also within 2 km: High Grove Solar (at pre-application, 542 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Breckland - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Breckland
Application type
FMIN minor application
Received
6 Oct 2026
Validated
21 Oct 2026
Ward
Swaffham
Parish
Swaffham
Case officer
Show
Target decision
16 Dec 2026
Decision level
Delegated decision
Applicant
Show
Agent
Chaplin Farrant Architects

Decision outlook

Day 33 of the 56-day target. Breckland usually decides commercial and major works by day 80.

Day 3347 days to the predicted decision (day 80)
40%decided within 8 weeks
88%approved
13%go to committee

Plota live figures for commercial and major works decided by Breckland in the last twelve months, from validation. Breckland decision record →

Consultation & key dates

Statutory expiry
16 Dec 2026
Breckland
Planning Authority Score
8.6/10
Excellent
#14 of 296 overall
Relevant to this application:
Householder decisions

Breckland is faster than most councils at deciding householder applications: #32 of 296 on speed. Householder applications are more likely to be approved here than most councils, with a 98% approval rate vs 90% nationally.

More permissive than most councils
98% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Breckland decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #216 of 296
98%
Householder approved
Above avg (90%) #12 of 296
81%
Decided in 8 weeks
Above avg (63%) #32 of 296
34%
Extended time limit
Below avg (41%) #84 of 296
54%
Minor dwellings approved
178 decided (1-9 homes)
88%
Major dwellings approved
17 decided (10+ homes)
801
Total decisions
128 refused in the year to March 2026