Flood assessment condition change at Morris Leslie Errol Airfield, Grange, Perth
Summary of planning committee decision
Decided by Perth Planning and Placemaking Committee on 14 Oct 2026.
What was proposed
The application sought to extend the deadline for submitting an updated flood risk assessment from six months to two years.
“1 This application relates to the development approved under planning permission 16/00999/AMM for 240 dwellings, a local centre, sports pitch and play area. The proposal seeks to amend Condition 7 (Flood Risk Assessment) attached to planning permission 25/01441/42M, which represents the most recent Section 42 (S42) approval for the development.”
“2 Within 6 months of the date of this consent, an updated Flood Risk Assessment shall be submitted to and agreed in writing by the Planning Authority. The Flood Risk Assessment shall include detailed designs of the proposed access road over the Pow of Errol. Additionally, details shall include garden levels, finished floor levels and soffit levels of all structures above ordnance datum. The details as agreed shall thereafter be implemented concurrent with development.”
Officer report
The site and development
The site is a mainly flat former airfield within the settlement boundary, approved for 240 homes, a local centre, sports pitch and play area.
“4 The site is located within the settlement boundary of Grange/Errol Airfield in the Perth and Kinross Local Development Plan 2 (2019) (LDP2) and is recorded as having planning permission for housing. The predominantly flat site extends to approximately 58.3 hectares, 0.75km northeast of Errol village. It forms part of the disused Errol Airfield facility which provides buildings for small businesses and there are some residential properties to the north of the site.”
“7 Planning Permission in Principle (PPP) was approved in October 2010 (05/02418/IPM) and extended in January 2014 (13/01823/FLM). Detailed permission was granted in July 2017 for 240 dwellings, a local centre, sports pitch and play area within the northern half of the PPP site (16/00999/AMM). Development of this site has commenced with the establishment of the approved acoustic bund along the northern boundary of the site.”
Officer report
Earlier permissions
Planning permission in principle was granted in 2010, detailed permission followed in 2017, and later Section 42 applications changed individual conditions.
“10 16/00999/AMM Mixed use development comprising the erection of 240 dwellinghouses/garages, erection of commercial elements, provision of open space/play provision, associated infrastructure and other associated works (approval of matters specified in conditions 13/01823/FLM). Approved by Planning & Development Management Committee July 2017.”
“12 20/00169/AMM Section 42 application to modify condition 15 (contamination) of permission 16/00999/AMM. Approved by Planning and Development Management Committee on 29 July 2020.”
Officer report
What officers recommended
Officers recommended approval because the revised condition would continue to require flood assessment details and comply with relevant flood-risk policies.
“39 The applicant proposes to amend the timeframe associated with Condition 7 (Flood Risk Assessment). Condition 7 currently requires an updated Flood Risk Assessment to be submitted to and approved in writing by the Planning Authority within six months of the date of the consent. The applicant now seeks to extend this timeframe from six months to two years, with the remainder of the condition remaining unchanged.”
“43 The Council's Structures and Flooding Team has reviewed the proposed variation to Condition 7 and raises no objection. It is considered that the revised condition will continue to ensure that an updated Flood Risk Assessment, including details of finished floor levels, garden levels and the proposed access road crossing, is submitted for approval prior to implementation.”
Officer report
Consultation responses
The airport, development plan, biodiversity and development contributions consultees made no comments, while roads and flooding consultees raised no objections.
“31 Transportation and Development – no objections.”
“32 Development Contributions Officer – no comments.”
Officer report
The committee decision
The committee granted the application subject to the listed terms, conditions and informatives, including a two-year deadline for the updated flood risk assessment.
“26/00943/42M - S42 application to modify condition 7 (flood risk assessment) of permission 25/01441/42M, Morris Leslie, Errol Airfield, Grange, Errol, Perth, PH2 7TB (Report No. 26/285)”
“Conditions 1. The development hereby approved shall be commenced not later than 11 March 2029. If development has not lawfully commenced by that date, the approval of matters specified in conditions lapses.”
Minutes
Councillors at the meeting
- Ian MassieChairSNPFor(no vote against recorded)
- Grant StewartSNPFor(no vote against recorded)
- Keith AllanConservativeFor(no vote against recorded)
- Bob BrawnConservativeFor(no vote against recorded)
- David IllingworthConservativeFor(no vote against recorded)
- Ian JamesConservativeFor(no vote against recorded)
- Ken HarveySNPFor(no vote against recorded)
- Claire McLarenLib DemFor(no vote against recorded)
- Mike WilliamsonSNPFor(no vote against recorded)
The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.
Apologies Dave Cuthbert Independent, Richard Watters SNP
Source: Plota analysis of the council's minutes; parties from Democracy Club.
Sources
- Perth Planning and Placemaking Committee minutes, 14 October 2026
- Agenda and papers (council website)
Source: Plota analysis of Perth's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Perth
- Date
- Wednesday 14 October 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Councillors
- 9Conservative 4SNP 4Lib Dem 1Show votes
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Perth committee decisions →
This committee's year
65 decisions in the 12 months to this meeting, 7 against officer advice.
Source: Plota analysis of the committee's minutes.