Co-living building at Hope Street, Cathays, Cardiff

Summary of planning committee decision

Decided by Cardiff Planning Committee on 4 Jun 2026.

25/02351/FULApproved

What was proposed

The application proposed a 33-storey, 102.3-metre co-living building with 400 units, shared facilities, infrastructure, landscaping and public realm works.

“Planning consent is sought for a 33-storey (102.3m high) co-living development comprising 400 units with associated amenity spaces, along with the provision of new infrastructure, landscaping, and public realm improvements. Each unit would measure between 21m 2 and 30m 2 , with the largest number (230 no) measuring 22m 2 .”

“The ground and part of the first floor would accommodate a publicly-accessible flexible co-working space, along with a bookable podcast studio. An outdoor terrace would also be provided on the ground floor. These facilities would serve both residents and the wider public. Gym facilities would be located on the third floor, alongside communal lounge, games and laundry area.”

Officer report

The site and surroundings

The 0.16-hectare brownfield site had been vacant for about three decades and was near Cardiff Central station, listed buildings, hotels and the railway.

“The application site comprises a parcel of land measuring 0.16 hectares, bound by Custom House Street to the north, Bute Street to the east, the mainline railway to the south, and Hope Street to the West. The site which has been in a vacant possession for approximately three decades, consists of hardstanding with some self-seeded shrubbery and two small electrical plant buildings, having been cleared of the previous buildings on this brownfield site.”

“The listed (Grade II) Gold Cross Public house sits immediately north of the site on the opposite side of Custom House Street, the Radisson Blu Hotel to the east, with the Unison and Open University building on the opposite site of Hope Street to the west. South of the railway lays Callaghan Square and surrounding commercial buildings including the office block to 1 Callaghan Square. Part of the site also currently comprises adopted highway (see figure 2 below).”

Officer report

Earlier planning history

Earlier permissions included a 42-storey, 447-bed student accommodation tower, later varied and supported by a certificate confirming a material start.

“Full planning permission for the redevelopment of the site for a mixed-use development comprising of purpose built student accommodation (447 bed spaces) and a retail / commercial unit (Classes A1 and A3) within a 42 storey tower, together with landscaping, ancillary and communal facilities Granted 14/07/2016”

“Full planning permission for the redevelopment of the site for a mixed-use development comprising of purpose built student accommodation (447 bed spaces) and a retail / commercial unit (Classes A1 and A3) within a 42 storey tower, together with landscaping , ancillary and communal facilities Granted 14/07/2016”

Officer report

What consultees said

Internal and external consultees generally raised no objection or supported the scheme subject to conditions, agreements, mitigation and further technical details.

“Raises no objection to the co-living development, noting its highly sustainable city- centre location, with policy compliant zero car parking provision, and acceptable cycle parking. The scheme requires stopping up parts of the adopted highway and delivering replacement footway/cycleway links and public realm works via S278/S38 agreements, all to be completed before occupation.”

“No objection is raised, but detailed upfront planting plans and planter specifications are required, including confirmation of drainage and irrigation arrangements. This is particularly important due to the reduced subsoil depth, which normally functions as a water reservoir and helps prevent both waterlogging and drought.”

Officer report

Public representations

The application was publicised through notices, letters, the website and local press, and no public representations had been received.

“The application was advertised on the Council Website and by way of neighbour notification letters, site notices and advertisement in the local press, with the closing dates for public consultation for each on the 10th, 13th and 20th November 2025. No public representations have been received to date.”

“All representations made on the application are available to view in full on the Council’s website at: - 25/02351/FUL”

Officer report

Meeting information

The application was identified by its reference and proposal, while the available meeting information places applications decided by delegated powers on the agenda.

“To note the applications decided by delegated powers between 8 th – 27 th May.”

Minutes

Councillors at the meeting

Apologies Helen Gunter Labour

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Cardiff Planning Committee minutes, 4 June 2026
  • Agenda and papers (council website)

Source: Plota analysis of Cardiff's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Cardiff
Date
Thursday 4 June 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
10Labour 6Conservative 2Independent 1Lib Dem 1Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

18 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →