01739/26/ABD - Prior Approval - Demolition Awaiting decision

Proposal

Application to determine whether Prior Approval is required for the demolition of a row of 3 Terrace houses Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
7 Oct 2026
✓
Validated
8 Oct 2026
✓
Consultation
8 Oct 2026
Decision
Target date was 4 Nov 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 20 Nov 2026; it is now day 43.

The consultation period closed on 29 Oct 2026.

Site constraints 6

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Agricultural land, grade 1
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 27 m away: Outer Dowsing Offshore Wind (Generating Station)
The site is 27 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Boston Alternative Energy Facility (BAEF) (decided, 2 km).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Expansion Zone
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Local nature reserve 429 m away: The Wash; SSSI 429 m away: The Wash SSSI.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area106 m² (1,141 sq ft)
Energy ratingE (52 out of 100), could reach A
PropertyEnd-terrace house, 6 habitable rooms
Built1950 to 1966
HeatingBoiler and radiators, dual fuel (mineral and wood)
WallsCavity wall, filled cavity

From the energy performance certificate lodged in January 2024, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Boston - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Boston
Application type
Prior Approval - Demolition
Postcode
PE20 1BD
Received
7 Oct 2026
Validated
8 Oct 2026
Parish
Wyberton
Case officer
Show
Target decision
4 Nov 2026
Applicant
Show
Agent
AE Lenton Ltd

Decision outlook

Day 43, past Boston's usual 35 days for prior approvals. 96% are decided within thirteen weeks, so most likely by 7 Jan 2027.

Day 4313 days to the 56-day target
92%decided within 8 weeks
77%approved
26decided in the last year

Plota live figures for prior approvals decided by Boston in the last twelve months, from validation. Boston decision record →

Public comments

1comment received
1 neutral

Last counted 19 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15278182
Planning Portal ref
PP-15278182
Consultation
8 Oct 2026
Comments by
29 Oct 2026
Statutory expiry
4 Nov 2026
Env. assessment
No

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.