Church Of St Remigius Norwich Road Hethersett Norfolk Data via plota.co.uk

2026/2058 - Approval of Condition Details Approved

Proposal

Details of condition 3 (March) of original planning application (Installation of 6 x 4m tall black lighting columns and 2 x car charging points) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
15 Jul 2026
✓
Validated
24 Jul 2026
✓
Consultation
27 Jul 2026
✓
Approved
15 Sept 2026

Approved on 15 Sept 2026 · Delegated · Last checked 17 Sept 2026

Associated applications 2

  • Part of

    Fullcouncil archive

    Conditions 3 discharged

    • ConditionsDetails of condition 3 (March) of original (Installation of 6 x 4m tall black lighting columns…This application2026/2058

Site constraints 7

Grade II listed: Hethersett War Memorial
List entry 1443937 · 15 m away · 1 more listed building within 150 m (1 Grade II*)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other one with distances
Historic England ↗
Nutrient neutrality catchment: Yare Broads and Marshes
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Public footpath 10 m away
Matters where it crosses or adjoins the site: obstructing a path without a diversion order is an offence, and work cannot start until the order is confirmed.
Compiled from highway authority data, not the legal definitive map. A few authorities have not published, so no path shown is not proof there is none.
National infrastructure project 530 m away: Hornsea Project Three Offshore Wind Farm
The site is 530 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: A47 - A11 Thickthorn Junction (decided, 576 m); Sheringham and Dudgeon Extension Projects (decided, 1640 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Hethersett built-up area; Priority habitat 14 m away: Deciduous woodland; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in South Norfolk Broadland - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Approval of Condition Details
Received
15 Jul 2026
Validated
24 Jul 2026
Ward
Hethersett
Parish
Hethersett
Case officer
Show
Target decision
18 Sept 2026
Decision
Approval of details - Approved
Decision date
15 Sept 2026
Decision level
Delegated
Applicant
Show
Agent
Birdsall, Swash & Blackman Ltd

How this decision compares

Decided in 53 days from validation, about the council's usual 52 days. Approved, as 100% of utility and infrastructure works here are.

63%decided within 8 weeks
100%approved
96decided in the last year

Plota live figures for utility and infrastructure works decided by South Norfolk Broadland in the last twelve months, from validation. South Norfolk Broadland decision record →

Public comments

No public comments yet.

Last counted 17 Sept 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15084190
Planning Portal ref
PP-15084190
Consultation
27 Jul 2026
Comments by
17 Aug 2026
Statutory expiry
18 Sept 2026
Env. assessment
No
South Norfolk Broadland
Planning Authority Score
5.9/10
Average
#106 of 296 councils
Relevant to this application:
Householder decisions

South Norfolk Broadland ranks #136 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
South Norfolk Broadland decision statistics
Based on MHCLG data, the year to March 2026
93%
Overall approval rate
Above avg (87%) #50 of 296
95%
Householder approved
Above avg (90%) #71 of 296
67%
Decided in 8 weeks
Above avg (63%) #136 of 296
42%
Extended time limit
Above avg (41%) #161 of 296
82%
Minor dwellings approved
137 decided (1-9 homes)
92%
Major dwellings approved
12 decided (10+ homes)
100%
Change of use approved
33 decided
1,013
Total decisions
67 refused in the year to March 2026