7 Coldbath Square, London, EC1R 5HL Data via plota.co.uk

P2025/2316/FUL - Full Planning Application OFFICER REVIEW

Proposal

Ancillary use of 2nd floor of office space for occasional overnight accommodation for staff and associated business users. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
11 Aug 2025
✓
Validated
23 Sept 2025
✓
Consultation
2 Oct 2025
Decision
Target date was 16 Nov 2025

Under consideration

No decision has been issued yet. Plota predicted a decision around 23 Nov 2026; it is now day 426.

The consultation period closed on 25 Oct 2025.

Site constraints 22

Article 4 directionCritical Drainage Group3_006Kenwood viewing gazebo to St Paul's CathedralBunhill & Clerkenwell Area Action PlanCAZHeathrow Safeguarding AreaCentral Activities ZoneMount PleasantParliament Hill summit to St Paul's CathedralSite within 100m of a TLRN RoadAPA Civil War DefencesWithin 50m of
Protected view corridor: 3A.1 Kenwood viewing gazebo to St Paul's Cathedral
Inside the landmark viewing corridor of a protected vista. A building that rises above the corridor's threshold height should be refused. How high that is depends on where along the view the site is. Also in the wider setting of 2A.1 Parliament Hill summit to St Paul's Cathedral.
The London Plan (policy HC4) designates strategic views, and the Mayor's London View Management Framework (March 2012) gives 13 of them a protected vista toward St Paul's Cathedral, the Palace of Westminster or the Tower of London. A vista has a threshold height that rises or falls with the line of sight. In the landmark viewing corridor, a building above it would harm the view and should be refused. In the wider setting consultation area around the corridor, a building above it is referred for consultation and its effect on the view is judged. The threshold changes along each view and is set out in the framework. A revised framework is out for consultation until 4 December 2026 and is not yet in force.
London View Management Framework ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Islington AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
9 listed buildings within 150 m
Nearest: Rosebery Avenue Bridge Viaduct, Grade II, 50 m away · 1 Grade II*, 7 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 9 with distances
Historic England ↗
Conservation area 18 m away: Rosebery Avenue
The edge of the area; work outside it can still affect its setting.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
National infrastructure project 1.1 km away: Thames Tideway Tunnel
The site is 1.1 km from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 1.5 km).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Article 4 directionCouncil record
Some permitted development rights are withdrawn. The direction is on the council's register but not published as open data.
Council site ↗
Critical Drainage Group3_006Council record
Recorded by the council for this site.
Council site ↗
Kenwood viewing gazebo to St Paul's CathedralCouncil record
Recorded by the council for this site.
Council site ↗
Bunhill & Clerkenwell Area Action PlanCouncil record
Recorded by the council for this site.
Council site ↗
CAZCouncil record
Recorded by the council for this site.
Council site ↗
Heathrow Safeguarding AreaCouncil record
Recorded by the council for this site.
Council site ↗
Central Activities ZoneCouncil record
Recorded by the council for this site.
Council site ↗
Mount PleasantCouncil record
Recorded by the council for this site.
Council site ↗
Parliament Hill summit to St Paul's CathedralCouncil record
Recorded by the council for this site.
Council site ↗
Site within 100m of a TLRN RoadCouncil record
Recorded by the council for this site.
Council site ↗
APA Civil War DefencesCouncil record
Recorded by the council for this site.
Council site ↗
Within 50m ofCouncil record
Recorded by the council for this site.
Council site ↗
Also on the record
Heritage at risk 46 m away: Clerkenwell; Inside the Islington built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area309 m² (3,326 sq ft)
Energy ratingD (asset rating 82)
UseOffices and Workshop Businesses
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in June 2022, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Islington - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Islington
Application type
Full Planning Application
Postcode
EC1R 5HL
Received
11 Aug 2025
Validated
23 Sept 2025
Ward
Clerkenwell
Case officer
Show
Target decision
16 Nov 2025
Freehold owner
Show

Decision outlook

Day 426, past the statutory target. 80% of full applications in Islington are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 17 Nov 2026.

Day 426370 days past the 56-day target
59%decided within 8 weeks
88%approved
704decided in the last year

Plota live figures for full applications decided by Islington in the last twelve months, from validation. Islington decision record →

Consultation & key dates

Alt. reference
PP-14246772
Comments by
25 Oct 2025
Site or press notice
2 Oct 2025
Statutory expiry
19 Oct 2025
Islington
Planning Authority Score
2.9/10
Poor
#237 of 296 overall
Relevant to this application:
Householder decisions

Islington is slower than most councils at deciding householder applications: #260 of 296 on speed. 53% of applications have the time limit extended, above the 41% national average. Householder applications are slightly more likely to be approved here (93%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Islington decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #132 of 296
93%
Householder approved
Above avg (90%) #130 of 296
43%
Decided in 8 weeks
Below avg (63%) #260 of 296
53%
Extended time limit
Above avg (41%) #241 of 296
89%
Minor dwellings approved
499 decided (1-9 homes)
100%
Major dwellings approved
1 decided (10+ homes)
89%
Change of use approved
19 decided
1,488
Total decisions
167 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.

Freehold owner: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.