Land West Of Ipswich Road Keswick Norfolk Data via plota.co.uk

Proposal

Construction of a data centre (Use Class B8) including ancillary office accommodation, associated infrastructure, substations, backup generators, access, parking, landscaping, sustainable drainage systems and associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
2 Oct 2026
✓
Consultation
16 Oct 2026
Decision
Expected by 1 Jan 2027

Under consideration

No decision has been issued yet. Plota predicts a decision between 4 Dec 2026 and 25 Dec 2026, from South Norfolk Broadland's recent commercial and major works.

The consultation period closed on 6 Nov 2026.

Documents 110

Statements & assessments 75

PDF Ob_vl_p26-3788_05 Air quality assessment Report (K) · 2 Oct 2026 View ↗ PDF Pca_enf147831 Post excavation assessment Report (K) · 2 Oct 2026 View ↗ PDF Biodiversity statement Report (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-xx-xx-rp-a-00001_part1 Design and access statement part 1 Report (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-xx-xx-rp-a-00001 Design and access statement part 3 Report (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-xx-xx-rp-a-00001 Design and access statement part 4 Report (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-xx-xx-rp-a-00001 Design and access statement part 2 Report (K) · 2 Oct 2026 View ↗ PDF Rbu2026n00422-ram-rp-00001 rev03 Energy statement Report (K) · 2 Oct 2026 View ↗ PDF Heritage statement Report (K) · 2 Oct 2026 View ↗ PDF Mt_vl_p26-3788_10 rev c Acoustic assessment Report (K) · 2 Oct 2026 View ↗ PDF Tjb_vl_p26-3788_02 rev a Phase 1 contaminated land assessment Report (K) · 2 Oct 2026 View ↗ PDF Planning statement Report (K) · 2 Oct 2026 View ↗ PDF Statement of community involvement Report (K) · 2 Oct 2026 View ↗ PDF V3 Sustainability statement Report (K) · 2 Oct 2026 View ↗ PDF Ma_vl_p26-3788_07 Transport assessment Report (K) · 2 Oct 2026 View ↗ PDF Tt_vl_p26-3788_06 rev b Flood risk assessment & drainage strategy vol 2 of 7 Report (K) · 2 Oct 2026 View ↗ PDF Tt_vl_p26-3788_06 rev b Flood risk assessment & drainage strategy vol 5 of 7 Report (K) · 2 Oct 2026 View ↗ PDF Tt_vl_p26-3788_06 rev b Flood risk assessment & drainage strategy vol 4 of 7 Report (K) · 2 Oct 2026 View ↗ PDF Tt_vl_p26-3788_06 rev b Flood risk assessment & drainage strategy vol 6 of 7 Report (K) · 2 Oct 2026 View ↗ PDF Tt_vl_p26-3788_06 rev b Flood risk assessment & drainage strategy vol 1 of 7 Report (K) · 2 Oct 2026 View ↗ PDF Tt_vl_p26-3788_06 rev b Flood risk assessment & drainage strategy vol 7 of 7 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix l - assessment of landscape susc Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix j - part 2 drawings Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix i - topographical survey and sit Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix j - part 1 drawings Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 19 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 17 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 16 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 18 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 20 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 24 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 22 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 26 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 23 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 25 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 27 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 28 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix h - part 3 technical methodology Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix k - assessment summary Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 5 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix b - calculation of theoretical v Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 1 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix a- figures v02 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 7 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 4 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 9 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 6 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 2 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 1 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 8 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 4 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 6b Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 7 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 6a Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visulaisations viewpoint 3 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 10 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 6c Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 8 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 9 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 12 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 11 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations - visualisati Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 15 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - viewpoint 13 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 2 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix c - viewpoints part 3 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix e - landscape assessment Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 5 Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix g - lvia methodology Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix f - visual assessment Report (K) · 2 Oct 2026 View ↗ PDF Landscape and visual impact assessment appendix d - visualisations viewpoint 21 Report (K) · 2 Oct 2026 View ↗ PDF Tt_vl_p26-3788_06 rev b Flood risk assessment & drainage strategy vol 3 of 7 Report (K) · 2 Oct 2026 View ↗ PDF Arboricultural impact assessment Report (K) · 2 Oct 2026 View ↗ PDF Ecological impact assessment report Report (K) · 2 Oct 2026 View ↗

Plans & drawings 30

PDF 1620019052-tpa-sw-00-dr-a-90000-p1 Site location plan Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0601-p04 Landscape detail plan - north Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0701-p03 Planting plan - north Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0602-p04 Landscape detail plan - west Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0702-p03 Planting plan - west Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0603-p04 Landscape detail plan - south Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0703-p03 Planting plan - south Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0801-p04 Sections a and b Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0803-p04 Sections e and f Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0804-p03 Section g Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0802-p05 Sections c and d Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-sh-l-0710-p04 Planting schedule Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0805-p03 Section h Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0806-p03 Section i Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-00-dr-a-20100-p1 General arrangements ground floor plan Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-02-dr-a-20102-p1 General arrangements main roof level Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-01-dr-a-20101-p1 General arrangements first floor plan Drawing (K) · 2 Oct 2026 View ↗ PDF 560-sfl-ex-00-dr-l-0501-p08 t Landscape plan general arrangement Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-zz-dr-a-21000-p1 General arrangement elevations Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-zz-dr-a-22000-p1 General arrangement sections Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-03-dr-a-20103-p1 General arrangements chiller gantry level plan Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-zz-dr-a-20111-p1 General arrangements site buildings plans, sections and elevations Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-zz-zz-dr-a-20110-p1 General arrangements generator plans, sections and elevations Drawing (K) · 2 Oct 2026 View ↗ PDF 1620019052-tpa-sw-03-dr-a-90004-p1 Site wide plan overall site Drawing (K) · 2 Oct 2026 View ↗ PDF Ma_vl_p26-3788_08 Travel plan Report (K) · 2 Oct 2026 View ↗ PDF Cb_vl_p26-3788_03 rev a Site waste management plan Report (K) · 2 Oct 2026 View ↗ PDF Aw_vl_p26-3788_04 Materials management plan Report (K) · 2 Oct 2026 View ↗ PDF Wg_vl_p26-3788_09 rev a Construction water management plan part 1 Drawing (K) · 2 Oct 2026 View ↗ PDF Wg_vl_p26-3788_09 rev a Construction water management plan part 2 Drawing (K) · 2 Oct 2026 View ↗ PDF Wg_vl_p26-3788_09 rev a Construction water management plan part 3 Drawing (K) · 2 Oct 2026 View ↗

All documents on the council site ↗

Site constraints 6

Nutrient neutrality catchment: Yare Broads and Marshes
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 3. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 208 m away: Sheringham and Dudgeon Extension Projects
The site is 208 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Hornsea Project Three Offshore Wind Farm (decided, 475 m); Norwich to Tilbury (examination closed, recommendation due, 532 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Expansion Zone
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Tree preservation order 10 m away: The Norfolk (Forehoe and Henstead Rural District) Stoke Holy Cross Tree Preservation Order 1964 No 1; Priority habitat 9 m away: Deciduous woodland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in South Norfolk Broadland - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full
Received
2 Oct 2026
Validated
2 Oct 2026
Ward
Cringleford
Parish
Keswick And Intwood
Case officer
Show
Target decision
1 Jan 2027
Applicant
Show
Agent
Ingleton Wood

Decision outlook

Day 40 of the 56-day target. South Norfolk Broadland usually decides commercial and major works by day 74.

Day 4034 days to the predicted decision (day 74)
32%decided within 8 weeks
90%approved
6%go to committee

Plota live figures for commercial and major works decided by South Norfolk Broadland in the last twelve months, from validation. South Norfolk Broadland decision record →

Public comments

707comments received
703 objecting3 neutral1 supporting

99% object · above the UK average of 74%

312 neighbours consulted · Last counted 5 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15262953
Planning Portal ref
PP-15262953
Neighbours
7 Oct 2026
Consultation
16 Oct 2026
Comments by
6 Nov 2026
Site or press notice
15 Oct 2026
Statutory expiry
1 Jan 2027
Env. assessment
No
South Norfolk Broadland
Planning Authority Score
5.9/10
Average
#106 of 296 councils
Relevant to this application:
Householder decisions

South Norfolk Broadland ranks #136 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
South Norfolk Broadland decision statistics
Based on MHCLG data, the year to March 2026
93%
Overall approval rate
Above avg (87%) #50 of 296
95%
Householder approved
Above avg (90%) #71 of 296
67%
Decided in 8 weeks
Above avg (63%) #136 of 296
42%
Extended time limit
Above avg (41%) #161 of 296
82%
Minor dwellings approved
137 decided (1-9 homes)
92%
Major dwellings approved
12 decided (10+ homes)
100%
Change of use approved
33 decided
1,013
Total decisions
67 refused in the year to March 2026