Royal Wolverhampton School Penn Road Wolverhampton West Midlands WV3 0EG Data via plota.co.uk

24/01124/LBD - Listed Building Demolition Approved

Proposal

Partial demolition, internal refurbishment, new entrance ramp and two storey extension of secondary school buildings (including works affecting a Grade II Listed building). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Oct 2024
✓
Consultation
20 Nov 2024
✓
Validated
29 Oct 2025
✓
Approved
11 Nov 2025

Approved on 11 Nov 2025 · Delegated Decision · Last checked 11 Oct 2026

Documents 201

Plans & drawings 180

PDF CORRIDOR SECTION-S3-P01 Drawings · 11 Nov 2025 View ↗ PDF SCHEDULE OF APPROVED PLANS FOR LISTED BUILDING CONSENT (REF: SOAP_2025 11 11 LBC Supporting Documents · 11 Nov 2025 View ↗ PDF SECONDARY INTERNAL DOOR TYPES Drawings · 15 Aug 2025 View ↗ PDF SECONDARY EXTERNAL DOOR TYPES Drawings · 15 Aug 2025 View ↗ PDF SECONDARY PROPOSED GA ELEVATIONS Drawings · 15 Aug 2025 View ↗ PDF SECONDARY PROPOSED SECOND FLOOR Drawings · 15 Aug 2025 View ↗ PDF SECONDARY DEMOLITION SECOND FLOOR Drawings · 15 Aug 2025 View ↗ PDF SECONDARY PROPOSED FIRST FLOOR Drawings · 15 Aug 2025 View ↗ PDF SECONDARY DEMOLITION FIRST FLOOR Drawings · 15 Aug 2025 View ↗ PDF SECONDARY PROPOSED GROUND FLOOR Drawings · 15 Aug 2025 View ↗ PDF SECONDARY DEMOLITION GROUND FLOOR Drawings · 15 Aug 2025 View ↗ PDF W20-WINDOWS-DRAWING-09.24 Drawings · 5 Aug 2025 View ↗ PDF SOLEAL_NEXT_DOOR Drawings · 5 Aug 2025 View ↗ PDF INTERNAL DOOR TYPES-S5-P03 Drawings · 5 Aug 2025 View ↗ PDF EXTERNAL DOOR TYPES-S5-P04 Drawings · 5 Aug 2025 View ↗ PDF DSSI DOORS BROCHURE_NOV 2024 Drawings · 5 Aug 2025 View ↗ PDF CRITTALL-WINDOWS-CONSUMER-BROCHURE-V4 Drawings · 5 Aug 2025 View ↗ PDF PROPOSED GA ELEVATIONS Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA FIRST FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA GROUND FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF BOARDING DEMOLITION GROUND FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_2 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_1 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA UPPER FIRST FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF DEMOLITION UPPER FIRST FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA MEZZANINE FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA FIRST FLOOR PLANN Drawings · 30 Mar 2025 View ↗ PDF DEMOLITION FIRST FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA GROUND FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF DEMOLITION GROUND FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED S&W GA ELEVATIONS Drawings · 30 Mar 2025 View ↗ PDF PROPOSED N&E GA ELEVATIONS. Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA SECTIONS Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ROOF PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA FIRST FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA GROUND FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED ELEVATIONS - SOUTH, WEST Drawings · 30 Mar 2025 View ↗ PDF PROPOSED ELEVATIONS - NORTH, EAST Drawings · 30 Mar 2025 View ↗ PDF PROPOSED FIRST FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GROUND FLOOR PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_8 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_7 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_6 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_5 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_4 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_3 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GA ELEVATIONS_2 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_9 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_8 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_7 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_6 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_5 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_4 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_3 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_2 Drawings · 30 Mar 2025 View ↗ PDF EXISTING ELEVATIONS_1 Drawings · 30 Mar 2025 View ↗ PDF PROPOSED SECOND FLOOR Drawings · 30 Mar 2025 View ↗ PDF DEMOLITION SECOND FLOOR Drawings · 30 Mar 2025 View ↗ PDF PROPOSED FIRST FLOOR Drawings · 30 Mar 2025 View ↗ PDF DEMOLITION FIRST FLOOR Drawings · 30 Mar 2025 View ↗ PDF SUBSTATION AND SWITCH ROOM Drawings · 30 Mar 2025 View ↗ PDF PROPOSED GROUND FLOOR Drawings · 30 Mar 2025 View ↗ PDF DEMOLITION GROUND FLOOR Drawings · 30 Mar 2025 View ↗ PDF COMBINED SITE PLANTING STRATEGY Drawings · 30 Mar 2025 View ↗ PDF COMBINED SITE PARKING PROVISION Drawings · 30 Mar 2025 View ↗ PDF COMBINED SITE PROPOSED EXTERNAL SPORTS PROVISION Drawings · 30 Mar 2025 View ↗ PDF COMBINED SITE PRESENTATION MASTERPLAN Drawings · 30 Mar 2025 View ↗ PDF COMBINED SITE BLOCK PLAN Drawings · 30 Mar 2025 View ↗ PDF PROPOSED LANDSCAPE WORKS Drawings · 30 Mar 2025 View ↗ PDF EXTERNAL SPORTS PROVISION Drawings · 30 Mar 2025 View ↗ PDF SITE MASTERPLAN Drawings · 30 Mar 2025 View ↗ PDF LEVELS STRATEGY Drawings · 30 Mar 2025 View ↗ PDF SECURE LINE STRATEGY Drawings · 30 Mar 2025 View ↗ PDF ACCESS STRATEGY Drawings · 30 Mar 2025 View ↗ PDF PROPOSED LANDSCAPE WORKS Drawings · 30 Mar 2025 View ↗ PDF PROPOSED LANDSCAPE WORKS Drawings · 30 Mar 2025 View ↗ PDF MASTERPLAN Drawings · 30 Mar 2025 View ↗ PDF SITE SECTIONS Drawings · 30 Mar 2025 View ↗ PDF SECURE LINE STRATEGY Drawings · 30 Mar 2025 View ↗ PDF ACCESS STRATEGY Drawings · 30 Mar 2025 View ↗ PDF PROPOSED LANDSCAPE WORKS - EAST AREA Drawings · 30 Mar 2025 View ↗ PDF PROPOSED LANDSCAPE WORKS - WEST AREA Drawings · 30 Mar 2025 View ↗ PDF LANDSCAPE WORKS Drawings · 30 Mar 2025 View ↗ PDF UTILITIES CONNECTIONS LAYOUT - DT BLOCK Drawings · 17 Nov 2024 View ↗ PDF UTILITIES CONNECTIONS LAYOUT - GIRLS DORMITORY Drawings · 17 Nov 2024 View ↗ PDF UTILITIES CONNECTIONS LAYOUT - BOYS DORMITORY Drawings · 17 Nov 2024 View ↗ PDF SITE MASTERPLAN Drawings · 17 Nov 2024 View ↗ PDF SECURE LINE STRATEGY Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ACCESS RAMP TO MAIN ENTRANCE Drawings · 17 Nov 2024 View ↗ PDF LEVELS STRATEGY Drawings · 17 Nov 2024 View ↗ PDF EXTERNAL SPORTS PROVISION Drawings · 17 Nov 2024 View ↗ PDF ACCESS STRATEGY Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_1 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_2 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_3 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_4 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_5 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_6 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_7 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_8 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED SECOND FLOOR Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ROOF FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED LANDSCAPE WORKS - MAIN BUILDING Drawings · 17 Nov 2024 View ↗ PDF PROPOSED GROUND FLOOR Drawings · 17 Nov 2024 View ↗ PDF PROPOSED FIRST FLOOR Drawings · 17 Nov 2024 View ↗ PDF UTILITIES CONNECTIONS LAYOUT - MAIN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED VISUAL 03 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED VISUAL 02 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED VISUAL 01 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED SECTIONS_2 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED SECTIONS_1. Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_9 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_8 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_7 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_6 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_5 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_4 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_3 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_2 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ELEVATIONS_1 Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING ROOF PLANS Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING SECOND FLOOR Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING FIRST FLOOR Drawings · 17 Nov 2024 View ↗ PDF SECONDARY EXISTING GROUND FLOOR Drawings · 17 Nov 2024 View ↗ PDF SECONDARY DEMOLITION SECOND FLOOR Drawings · 17 Nov 2024 View ↗ PDF SECONDARY DEMOLITION GROUND FLOOR Drawings · 17 Nov 2024 View ↗ PDF SECONDARY DEMOLITION FIRST FLOOR Drawings · 17 Nov 2024 View ↗ PDF PROPOSED VISUAL 04 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED VISUAL 03 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED VISUAL 02 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED VISUAL 01 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED SECTIONS Drawings · 17 Nov 2024 View ↗ PDF PROPOSED S AND W ELEVATIONS Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ROOF PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED N AND E ELEVATIONS Drawings · 17 Nov 2024 View ↗ PDF PROPOSED LANDSCAPE WORKS Drawings · 17 Nov 2024 View ↗ PDF PROPOSED GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING ROOF PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING ELEVATIONS Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION PLANS Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING ELEVATIONS Drawings · 17 Nov 2024 View ↗ PDF EXISTING ROOF PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED SECTIONS Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ROOF PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION UPPER FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION MEZZANINE FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION LOWER GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF DEMOLITION FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING UPPER FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING ROOF PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING MEZZANINE FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING LOWER GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF EXISTING ELEVATIONS_2 Drawings · 17 Nov 2024 View ↗ PDF EXISTING ELEVATIONS_1 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED UPPER FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED SECTIONS Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ROOF PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED MEZZANINE FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED LOWER GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED GROUND FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED FIRST FLOOR PLAN Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_2 Drawings · 17 Nov 2024 View ↗ PDF PROPOSED ELEVATIONS_1 Drawings · 17 Nov 2024 View ↗ PDF SITE MASTERPLAN Drawings · 17 Nov 2024 View ↗ PDF SITE LOCATION PLAN Drawings · 17 Nov 2024 View ↗ PDF FS0433A-DHL-ZZ-ZZ-D-L-9110 P03 SITE LOCATION PLAN Location Plan · 22 Oct 2024 View ↗ PDF FS0433A-DHL-ZZ-ZZ-D-L-9111 P03 - COMBINED SITE BLOCK PLAN Drawings · 22 Oct 2024 View ↗

All documents on the council site ↗

Site constraints 6

Grade II listed: Royal Wolverhampton School
List entry 1207637 · 5 m away · 5 more listed buildings within 150 m (5 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 5 with distances
Historic England ↗
Air quality management area: Wolverhampton Air Quality Management Area 2005
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Also on the record
Radon affected area, class 4; Nature improvement area: Birmingham and the Black Country; Coalfield, development low risk area; Inside the Wolverhampton built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area78 m² (840 sq ft)
Energy ratingE (45 out of 100), could reach D
PropertySemi-detached house, 4 habitable rooms
BuiltBefore 1900
HeatingBoiler and radiators, mains gas
WallsSolid brick, as built, no insulation (assumed)

From the energy performance certificate lodged in May 2011, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Wolverhampton - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Listed Building Demolition
Postcode
WV3 0EG
Received
22 Oct 2024
Validated
29 Oct 2025
Ward
Blakenhall
Case officer
Show
Target decision
28 Jan 2026
Decision
Grant
Decision date
11 Nov 2025
Decision level
Delegated Decision
Applicant
Show
Agent
Define Planning & Design Ltd

How this decision compares

Decided in 13 days from validation, 29 days faster than Wolverhampton's median of 42 for listed building consent. Approved, as 100% of listed building consent here are.

68%decided within 8 weeks
100%approved
29decided in the last year

Plota live figures for listed building consent decided by Wolverhampton in the last twelve months, from validation. Wolverhampton decision record →

Public comments

No public comments yet.

Last counted 11 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-13068607
Planning Portal ref
PP-13068607
Comments by
14 Dec 2024
Site or press notice
20 Nov 2024
Statutory expiry
28 Jan 2026
Env. assessment
No
Wolverhampton
Planning Authority Score
6.7/10
Good
#74 of 296 overall
Relevant to this application:
Other decisions

Wolverhampton is #100 of 296 councils on householder decision speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Wolverhampton decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #146 of 296
95%
Householder approved
Above avg (90%) #96 of 296
73%
Decided in 8 weeks
Above avg (63%) #100 of 296
34%
Extended time limit
Below avg (41%) #97 of 296
77%
Minor dwellings approved
61 decided (1-9 homes)
93%
Major dwellings approved
14 decided (10+ homes)
64%
Change of use approved
56 decided
817
Total decisions
89 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.