Phased site remediation at Site To West And South Of Mains Bungalow Eglinton, Irvine
Summary of planning committee decision
Decided by North Ayrshire Planning Committee on 18 Mar 2026.
What was proposed
The applicant sought to vary condition 5 so site remediation could be carried out in phases before building each part of the development.
“Condition 5 requires that the entire site is remediated before any houses can be built. This condition was recommended by The Coal Authority to make the ground safe and stable for building on in the interests of health and safety.”
“Keepmoat Homes now seeks permission to carry out the remediation work on a phased basis. They state that the site would be developed in three phases, as per the 2025 planning permission. They advise that carrying out the remediation work on a phased basis in advance of construction would be more efficient and cost effective than carrying the entire operation in advance of building any houses.”
Officer report
The site and earlier permission
The site is west and south of Mains Bungalow, and permission was previously granted for 255 houses at Montgomerie Park.
“Site to west and south of Mains Bungalow, Irvine Applicant…”
“The Council's Planning Committee granted permission, subject to conditions, for the development of 255 dwellinghouses on allocated housing land at Montgomerie Park, Irvine, on 28th August 2025 under ref. 25/00287/PPM.”
Officer report
Why approval was advised
The phased approach was considered reasonable, environmentally beneficial and supportive of housing delivery while retaining health and safety safeguards.
“As noted above, the use of planning conditions must be in accordance with the tests set out in Circular 4/1998. The proposed amendments to condition 5 would meet all six tests. As the development involves the construction of 255 houses along with all associated infrastructure, it is reasonable for a phased approach to be taken with regard to site remediation operations.”
“The delivery of major housing sites identified in the adopted LDP remains a key priority for the Council, particularly in relation to its strategic policies of stimulating population growth and economic development as part of the regeneration of North Ayrshire. Montgomerie Park is one of several Strategic Development Areas identified in the LDP.”
Officer report
Responses from neighbours
Two representations raised concerns about plot arrangements, services and road access, but these matters did not concern the proposed condition change.
“Response: The above points are not relevant to the current application. Planning permission has been granted and it is not proposed to change the layout at this stage. The only matter under consideration is the proposed change to the text of condition 5.”
“Concerned that Taylor Drive will become a through road for the Keepmoat site residents (and others). It seems unfair that Montgomerie Park Drive will essentially end at the junction of Armour Road and Taylor Drive, and Taylor Drive will become thoroughfare for these new sites. A preference is expressed that Montgomerie Park Drive would be continued to allow Keepmoat and NAC resident access without the need to travel through the Bellway site.”
Officer report
Committee discussion
Officers answered members’ questions before the committee considered the application.
“Submitted a report by the Chief Planning Officer under Section 42 of the Town and Country Planning (Scotland) Act 1997 seeking permission to vary condition 5 of planning permission 25/00287/PPM to enable the phasing of site remediation operations.”
“Officers responded to Members’ questions and the Committee unanimously agreed to approve planning permission.”
Minutes
The decision and conditions
Planning permission was approved subject to conditions, including phased remediation and confirmation that each completed residential phase was safe and stable.
“Condition 5. That the development hereby approved shall not commence until the remediation works for each phase of development (outlined in Section 9 of the Ground Investigation Report incorporating Coal Mining Risk Assessment (CMRA): Rev 1, YG695/03/MAK/CMB/KM/JC, dated April 2025) and/or mitigation measures to address land instability arising from coal mining legacy, as may be necessary, have been implemented for that phase, to ensure that the relevant part of the site is…”
“Thereafter, and prior to the occupation of any part of the development within a completed residential phase, a signed statement or declaration prepared by a suitably competent person confirming that that phase of the site, or has been made, safe and stable for the approved development shall be submitted for the written approval of North Ayrshire Council as Planning Authority.”
Officer report
Councillors at the meeting
- Robert FosterLabourFor
- Cameron InglisConservativeFor
- Stewart FergusonConservativeFor
- Ronnie StalkerConservativeFor
- Scott DavidsonSNPFor
- Margaret JohnsonSNPFor
- Amanda KerrLabourFor
- Davina McTiernanSNPFor
- Jim MontgomerieLabourFor
From a unanimous vote of the 9 members present for this item.
Apologies Ian Murdoch Independent
Source: Plota analysis of the council's minutes; parties from Democracy Club.
Sources
- North Ayrshire Planning Committee minutes, 18 March 2026
- Agenda and papers (council website)
Source: Plota analysis of North Ayrshire's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- North Ayrshire Planning Committee
- Council
- North Ayrshire
- Date
- Wednesday 18 March 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- Unanimous
- Councillors
- 9Conservative 3Labour 3SNP 3Show votes
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- North Ayrshire committee decisions →
This committee's year
7 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.