Greenwich Railway Station, Greenwich High Road, Greenwich, SE10 8JQ Data via plota.co.uk

25/3740/L - Listed Building Consent Approved

Proposal

Repainting of the internal and external elements of the Greenwich Train Station in a heritage sensitive manner. The Areas of painting includes: ? The Booking Hall, including walls, columns, and timber joinery; ? The toilet area, including paneling and door/window frames; ? External window surrounds, quoins, plinths, and brick work; ? Platform 1 decorative features. The paint types would be applied to the areas as follows: Walls - Dulux trade diamond matt Joinery ? Dulux trade wood primer, dulux trade undercoats, dulux trade gloss Ceiling - Dulux trade diamond matt The paint colours are: Hollybush Green (BS 14 C 39) Cream White (BS 10 B 15). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
6 Nov 2025
✓
Consultation
20 Nov 2025
✓
Approved
29 Dec 2025

Approved on 29 Dec 2025 · Delegation · Last checked 1 Nov 2026

Site constraints 12

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 190 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Greenwich AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Greenwich West
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
5 listed buildings within 150 m; Radon affected area, class 2; Local nature reserve 447 m away: Sue Godfrey Nature Park; Conservation area 67 m away: Blackheath; Inside the Greenwich built-up area; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Greenwich - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Greenwich
Application type
Listed Building Consent
Postcode
SE10 8JQ
Received
6 Nov 2025
Validated
6 Nov 2025
Ward
GREENWICH PARK
Parish
Greenwich
Case officer
Show
Target decision
1 Jan 2026
Decision
Approve
Decision date
29 Dec 2025
Decision level
Delegation
Applicant
Show
Agent
Invvu Construction Consultants

How this decision compares

Decided in 53 days from validation, about the council's usual 56 days. Approved, as 91% of listed building consent here are.

52%decided within 8 weeks
91%approved
68decided in the last year

Plota live figures for listed building consent decided by Greenwich in the last twelve months, from validation. Greenwich decision record →

Public comments

No public comments yet.

Last counted 1 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14319815
Planning Portal ref
PP-14319815
Consultation
20 Nov 2025
Comments by
17 Dec 2025
Statutory expiry
1 Jan 2026
Env. assessment
No
Greenwich
Planning Authority Score
5.4/10
Average
#123 of 296 councils
Relevant to this application:
Other decisions

Greenwich is faster than most councils at deciding householder applications, ranking #76 out of 296. Only 29% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Greenwich is also one of the strictest councils - it refuses more householder applications than almost any other, with only 78% approved vs 90% nationally.

One of the strictest councils
only 78% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Greenwich decision statistics
Based on MHCLG data, the year to March 2026
77%
Overall approval rate
Below avg (87%) #278 of 296
78%
Householder approved
Below avg (90%) #287 of 296
75%
Decided in 8 weeks
Above avg (63%) #76 of 296
29%
Extended time limit
Below avg (41%) #49 of 296
60%
Minor dwellings approved
114 decided (1-9 homes)
100%
Major dwellings approved
13 decided (10+ homes)
66%
Change of use approved
195 decided
1,468
Total decisions
331 refused in the year to March 2026