BONT NEWYDD BRIDGE Bont Newydd, Cefn, St Asaph, Denbighshire Data via plota.co.uk

31/2026/0323/LBC - Listed Building Consent Approved

Proposal

Gwaith cryfhau ac atgyweirio ar y bont bresennol (cais Adeilad Rhestredig) / Strengthening and repair works to existing bridge (Listed Building application) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
30 Jun 2026
✓
Approved
8 Oct 2026

Approved on 8 Oct 2026 · Dirprwyedig/Delegated · Last checked 19 Oct 2026

Site constraints 6

Grade II listed: Bont Newydd (partly in Llannefydd community)
List entry 19927 · 4 m away · 2 more listed buildings within 150 m (2 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 2 with distances
Cadw ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
National infrastructure project 505 m away: North Wales Wind Farms Connection
The site is 505 m from the project boundary. Electricity line, decided. The project page says whether consent was granted. Also within 2 km: Mona Offshore Wind Farm (decided, 1.7 km); SP Mid Wales (Electricity) Connections Project (SP Manweb) (at pre-application, 979 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Special area of conservation 205 m away: Coedwigoedd Dyffryn Elwy / Elwy Valley Woods
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
Radon affected area, class 5
An estimated 10 to 30% of homes reach the radon action level. Indicative for the 1 km square, which takes the highest class found in it; a radon test gives the answer for a building.
From the British Geological Survey and UK Health Security Agency indicative atlas. Under building regulations, as the BRE guide BR 211 (2023) sets out, new buildings and extensions need basic radon protection from class 3 in England and Wales and from class 2 in Scotland, and full protection from class 5. The class at the site itself, from the detailed BGS map, decides which.
UKHSA radon ↗
Also on the record
SSSI 205 m away: Coedydd ac Ogofau Elwy a Meirchion.
Not affected
No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Denbighshire - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Listed Building Consent
Received
30 Jun 2026
Validated
30 Jun 2026
Ward
WD31 - Trefnant
Parish
Cefn Meiriadog CC (31)
Case officer
Show
Target decision
25 Aug 2026
Decision
Granted
Decision date
8 Oct 2026
Decision level
Dirprwyedig/Delegated
Applicant
Show
Agent
Conwy County Borough Council

How this decision compares

Decided in 100 days from validation, 29 days faster than Denbighshire's median of 129 for listed building works. Approved, as 97% of listed building works here are.

16%decided within 8 weeks
97%approved
33decided in the last year

Plota live figures for listed building works decided by Denbighshire in the last twelve months, from validation. Denbighshire decision record →

Consultation & key dates

Statutory expiry
25 Aug 2026