Land to North of Colchester Road Elmstead Essex CO7 7EF Data via plota.co.uk

26/00287/OUT - Outline Application Approved at committee

Approved at planning committee on 29 September 2026, subject to a legal agreement. The council issues its decision notice once the agreement is signed.

Proposal

Outline Planning Application (access to be considered) - for up to 30 dwellings and associated infrastructure including public open space, landscaping, and sustainable drainage. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
19 Feb 2026
✓
Validated
2 Mar 2026
✓
Consultation
3 Aug 2026
✓
Committee
29 Sept 2026
Decision notice
Not issued yet

Under consideration

No decision has been issued yet. Plota predicted a decision around 18 Nov 2026; it is now day 261.

A re-consultation started on 3 Aug 2026. The council has not yet published the new comment deadline.

Planning committee

Decided by Tendring Planning Committee on 29 Sept 2026. Earlier deferred on 7 Jul 2026. The council has not yet issued its decision notice.

Approved

  • Officers advised approval because housing, economic and social benefits outweighed limited, manageable environmental harm.
  • The parish council and residents raised concerns about policy conflict, traffic, access, infrastructure, landscape and effects on Meadow Close.
  • The committee authorised outline approval subject to a legal agreement and conditions, with refusal possible if obligations were not secured within 12 months.
Read how the committee decided The proposal, site context, officer assessment, objections, committee debate and decision.

Source: Plota analysis of Tendring's committee minutes of 29 Sept 2026.

Documents 86

Statements & assessments 28

PDF Consultee response - ecc heritage - rec'd 25.03.26 Consultee Comment · 26 Mar 2026 View ↗ PDF Consultee response - ecc ecology - rec'd 26.03.26 Consultee Comment · 26 Mar 2026 View ↗ PDF Habitat regulation assessment BackGround Papers · 16 Mar 2026 View ↗ PDF Bng metric - rec'd 18.02.26 Other · 24 Feb 2026 View ↗ PDF Planning statement - rec'd 19.02.26 Report · 24 Feb 2026 View ↗ PDF Phase 1 geo-environmental assessment - rec'd 19/02/26 Report · 24 Feb 2026 View ↗ PDF Transport assessment - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Flood risk assessment 1 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Flood risk assessment 2 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Flood risk assessment 3 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 1 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 2 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 4 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 6 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 8 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Design and access statement part 2 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Ecological impact assessment - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Historic environment desk based assessment - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Arboricultural implications assessment - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Geophysical survey - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 3 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 5 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 7 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Bng statement - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 9 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Utilities statement 10 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Design and access statement part 1 - rec'd 19.02.26 Report · 23 Feb 2026 View ↗ PDF Hedgerow regulations assessment - rec'd 19.02.26 Report · 23 Feb 2026 View ↗

Consultation & comments 32

PDF Objector’s name hidden Show Objection Comment · 29 Jun 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 26 Jun 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 25 Jun 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 24 Jun 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 24 Jun 2026 View ↗
PDF Consultee response - ecc suds - rec'd 16.06.26 Consultee Comment · 16 Jun 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 4 Jun 2026 View ↗
PDF Ecc highways - rec'd 02/06/2026 Consultee Comment · 2 Jun 2026 View ↗
PDF Objector’s name hidden Show Public Comment · 21 Apr 2026 View ↗
PDF Commenter’s name hidden Show Public Comment · 14 Apr 2026 View ↗
PDF Consultee response - environmental protection - rec'd 08.04.26 Consultee Comment · 9 Apr 2026 View ↗ PDF Consultee response - ecc suds - rec'd 09.04.26 Consultee Comment · 9 Apr 2026 View ↗ PDF Consultee response - anglian water services - rec'd 09.04.26 Consultee Comment · 9 Apr 2026 View ↗ PDF Consultee response - ecc suds - rec'd 08.04.2026 Consultee Comment · 8 Apr 2026 View ↗ PDF Consulteecomment Consultee Comment · 2 Apr 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 31 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 27 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 26 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 25 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 24 Mar 2026 View ↗
PDF Consulteecomment Consultee Comment · 24 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 23 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 23 Mar 2026 View ↗
PDF Consutlee response - ecc green infrastructure - rec'd 19.03.2026 Consultee Comment · 20 Mar 2026 View ↗ PDF Consultee response - uu open spaces - rec'd 18.03.2026 Consultee Comment · 19 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 18 Mar 2026 View ↗
PDF Consulteecomment Consultee Comment · 18 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 18 Mar 2026 View ↗
PDF Consultee response - essex county fire officer - rec'd 16.03.2026 Consultee Comment · 17 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 11 Mar 2026 View ↗
PDF Objector’s name hidden Show Objection Comment · 10 Mar 2026 View ↗
PDF Consultee response - north essex parking partnership - rec'd 06.03.2026 Consultee Comment · 9 Mar 2026 View ↗

All documents on the council site ↗

Site constraints 1

Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 1. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 3 November 2026. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tendring - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Tendring
Application type
Outline Application
Postcode
CO7 7EF
Received
19 Feb 2026
Validated
2 Mar 2026
Ward
Alresford & Elmstead
Parish
Elmstead Market Parish Council
Case officer
Show
Target decision
24 Dec 2026
Applicant
Show
Agent
Rosanna Metcalfe - Savills

Decision outlook

Day 261, past the statutory target. 80% of new homes in Tendring are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 17 Nov 2026.

Day 261170 days past the 91-day target
55%decided within 8 weeks
67%approved
6%go to committee

Plota live figures for new homes decided by Tendring in the last twelve months, from validation. Tendring decision record →

Public comments

57comments received
55 objecting1 neutral1 supporting

96% object · above the UK average of 74%

18 neighbours consulted · Last counted 17 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14671399
Planning Portal ref
PP-14671399
Neighbours
5 Mar 2026
Consultation
3 Aug 2026
Comments by
9 Apr 2026
Site or press notice
17 Mar 2026
Committee
29 Sept 2026
Statutory expiry
1 Jun 2026
Env. assessment
No
Tendring
Planning Authority Score
6.8/10
Good
#70 of 296 councils
Relevant to this application:
Major dwellings

Tendring is faster than most councils at deciding householder applications, ranking #40 out of 296. Only 26% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly less likely to be approved here (89%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tendring decision statistics
Based on MHCLG data, the year to March 2026
85%
Overall approval rate
Below avg (87%) #212 of 296
89%
Householder approved
Below avg (90%) #211 of 296
80%
Decided in 8 weeks
Above avg (63%) #40 of 296
26%
Extended time limit
Below avg (41%) #38 of 296
71%
Minor dwellings approved
114 decided (1-9 homes)
88%
Major dwellings approved
16 decided (10+ homes)
80%
Change of use approved
49 decided
837
Total decisions
127 refused in the year to March 2026