The Portland 65 Paragon Street Kingston Upon Hull HU1 3PE Data via plota.co.uk

25/00558/FULL - Full Planning Permission Approved

Proposal

Change of use from Student accommodation to a Large HMO (Sui Generis) (119 bedrooms), change of use of ground floor bar (Sui Generis) to commercial (class E), subdivision of the existing ground floor commercial unit (Class E) and external alterations including the addition of windows. (Revised Scheme) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
19 Jun 2025
✓
Approved
27 Feb 2026

Approved on 27 Feb 2026 · Committee Decision · Last checked 2 Nov 2026

Documents 132

Plans & drawings 44

PDF FINAL SECTION 106 AGREEMENT BackGround Papers · 30 Jan 2026 View ↗ PDF NORTH ELEVATION AS PROPOSED_P03 Drawing · 21 Nov 2025 View ↗ PDF GA SECTION 2 AS PROPOSED_P02 Drawing · 21 Nov 2025 View ↗ PDF SOUTH ELEVATION AS PROPOSED_P03 Drawing · 21 Nov 2025 View ↗ PDF GA SECTION 1 AS PROPOSED_P02 Drawing · 21 Nov 2025 View ↗ PDF UPDATED FLOOR PLAN Drawing · 27 Aug 2025 View ↗ PDF PARAGON STREET FIRST FLOOR DETAILED WINDOW ELEVATION Drawing · 11 Aug 2025 View ↗ PDF PARAGON STREET SECOND FLOOR DETAILED WINDOW ELEVATION Drawing · 11 Aug 2025 View ↗ PDF 1ST FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF TRAVEL PLAN Report · 19 Jun 2025 View ↗ PDF DOCUMENT ISSUE REGISTER Drawing · 19 Jun 2025 View ↗ PDF SITE LOCATION PLAN Drawing · 19 Jun 2025 View ↗ PDF 2ND FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF 2ND FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF 3RD FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF 3RD FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF 4TH FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF 4TH FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF 5TH FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF 5TH FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF 6TH FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF 6TH FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF 7TH FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF 7TH FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF ROOF PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF ROOF PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF NORTH ELEVATION AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF EAST ELEVATION AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF SOUTH ELEVATION AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF WEST ELEVATION AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF NORTH ELEVATION AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF EAST ELEVATION AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF SOUTH ELEVATION AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF WEST ELEVATION AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF GA SECTION 1 AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF GA SECTIONS 2 AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF GA SECTION 1 AS PROOSED Drawing · 19 Jun 2025 View ↗ PDF GA SECTION 2 AS PROOSED Drawing · 19 Jun 2025 View ↗ PDF SITE WIDE FIRE TENDER ACCESS PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF SITE PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF SITE PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF GROUND FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗ PDF GROUND FLOOR PLAN AS PROPOSED Drawing · 19 Jun 2025 View ↗ PDF 1ST FLOOR PLAN AS EXISTING Drawing · 19 Jun 2025 View ↗

Consultation & comments 30

PDF Objector’s name hidden Show Correspondence · 3 Dec 2025 View ↗
PDF PUBLIC COMMENT Correspondence · 7 Nov 2025 View ↗ PDF HUMBERSIDE POLICE RESPONSE 13 10 2025 Correspondence · 15 Oct 2025 View ↗ PDF PUBLIC COMMENT - MP Correspondence · 2 Sept 2025 View ↗ PDF COMMENTS Correspondence · 29 Aug 2025 View ↗ PDF COMMENTS Correspondence · 29 Aug 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 22 Aug 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 22 Aug 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 22 Aug 2025 View ↗
PDF ACCESS OFFICERS COMMENTS Correspondence · 21 Aug 2025 View ↗ PDF PUBLIC COMMENT Public Comment · 4 Aug 2025 View ↗ PDF EQUALITY OFFICER COMMENTS Correspondence · 4 Aug 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 4 Aug 2025 View ↗
PDF PUBLIC HEALTH COMMENTS Correspondence · 29 Jul 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 23 Jul 2025 View ↗
PDF ACCESS OFFICER COMMENTS Correspondence · 21 Jul 2025 View ↗ PDF POLICE COMMENTS Correspondence · 21 Jul 2025 View ↗ PDF CONSERVATION COMMENTS Correspondence · 21 Jul 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 19 Jul 2025 View ↗
PDF HIGHWAYS DC COMMENTS Correspondence · 15 Jul 2025 View ↗ PDF ENVIRONMENT HEALTH COMMENTS Correspondence · 14 Jul 2025 View ↗ PDF PUBLIC COMMENT Public Comment · 14 Jul 2025 View ↗ PDF URBAN DESIGN COMMENTS Correspondence · 11 Jul 2025 View ↗ PDF CAAC COMMENTS Correspondence · 8 Jul 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 8 Jul 2025 View ↗
PDF ENVIRONMENT AGENCY COMMENTS Correspondence · 30 Jun 2025 View ↗ PDF PUBLIC COMMENT Public Comment · 26 Jun 2025 View ↗ PDF PUBLIC COMMENT Public Comment · 25 Jun 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 24 Jun 2025 View ↗
PDF Commenter’s name hidden Show Public Comment · 24 Jun 2025 View ↗

Other documents 40

PDF S106 AGREEMENT BackGround Papers · 19 Feb 2026 View ↗ PDF LEGAL AGREEMENT Other · 28 Jan 2026 View ↗ PDF CLLR CTTEE LETTER Correspondence · 26 Nov 2025 View ↗ PDF CTTEE LETTER TO REPRESENTEES Correspondence · 26 Nov 2025 View ↗ PDF CTTEE LETTER TO AGENT Correspondence · 24 Nov 2025 View ↗ PDF EMAIL THREAD Correspondence · 21 Nov 2025 View ↗ PDF PETITION Correspondence · 7 Nov 2025 View ↗ PDF EMAIL 13 10 2025 17.10 Correspondence · 15 Oct 2025 View ↗ PDF SECURITY STRATEGY PROPOSALS Report · 13 Oct 2025 View ↗ PDF AGENT EMAIL 10 SEP 25 Correspondence · 15 Sept 2025 View ↗ PDF AGENT EMAIL 4 SEP 25 Correspondence · 12 Sept 2025 View ↗ PDF EMAIL Correspondence · 4 Sept 2025 View ↗ PDF AGENT EMAIL 01/09/2025 Correspondence · 2 Sept 2025 View ↗ PDF E-MAIL FROM ACCESS OFFICER Correspondence · 1 Sept 2025 View ↗ PDF REGISTER TO SPEAK AT COMMITTEE Correspondence · 1 Sept 2025 View ↗ PDF EMAIL Correspondence · 29 Aug 2025 View ↗ PDF CLLR CALL IN CTTEE LETTER Correspondence · 22 Aug 2025 View ↗ PDF CTTEE LETTER TO REPRESENTEES Correspondence · 22 Aug 2025 View ↗ PDF CTTEE LETTER TO AGENT Correspondence · 22 Aug 2025 View ↗ PDF HMO - SPD Report · 12 Aug 2025 View ↗ PDF EMAILS TO URBAN DESIGN 12/08/2025 Correspondence · 12 Aug 2025 View ↗ PDF WINDOW STUDY Other · 11 Aug 2025 View ↗ PDF E-MAIL FROM AGENT Correspondence · 11 Aug 2025 View ↗ PDF EMAILS TO ACCESS OFFICER 04/08/2025 Correspondence · 4 Aug 2025 View ↗ PDF REQUEST FOR MORE INFORMATION Correspondence · 30 Jul 2025 View ↗ PDF EMAIL Correspondence · 25 Jul 2025 View ↗ PDF EMAIL Correspondence · 25 Jul 2025 View ↗ PDF EMAIL Correspondence · 25 Jul 2025 View ↗ PDF EMAIL Correspondence · 24 Jul 2025 View ↗ PDF OPEN SPACE REQUIREMENTS Correspondence · 17 Jul 2025 View ↗ PDF EMAIL Correspondence · 10 Jul 2025 View ↗ PDF PRESS NOTICE Other · 9 Jul 2025 View ↗ PDF E-MAIL FROM AGENT Correspondence · 30 Jun 2025 View ↗ PDF E-MAIL FROM AGENT Correspondence · 30 Jun 2025 View ↗ PDF EMAIL CLLR CTTEE CALL IN 27/06/2025 Correspondence · 30 Jun 2025 View ↗ PDF E-MAIL FROM AGENT Correspondence · 30 Jun 2025 View ↗ PDF CHECKSHEET BackGround Papers · 24 Jun 2025 View ↗ PDF EMAIL WITH APPLICANT Correspondence · 24 Jun 2025 View ↗ PDF COVERING LETTER Other · 19 Jun 2025 View ↗ PDF A SUMMARY OF THE ATTACHMENTS IN THE PROPOSAL BackGround Papers · 19 Jun 2025 View ↗

All documents on the council site ↗

Site constraints 6

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Paragon conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
National infrastructure project 31 m away: A63 Castle Street Improvement-Hull
The site is 31 m from the project boundary. Highway, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
13 listed buildings within 150 m
Nearest: 10, Parliament Street, Grade II, 33 m away · 1 Grade II*, 12 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 13 with distances
Historic England ↗
Also on the record
Inside the Kingston upon Hull built-up area; Air quality management area 41 m away: Hull AQMA No.1(A).
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £400,000 in August 2018. Other property, leasehold.

17 August 2018£400,000Recorded as a transfer outside a standard sale

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Work with planning data?

Every application in Hull - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Hull
Application type
Full Planning Permission
Postcode
HU1 3JP
Received
19 Jun 2025
Validated
19 Jun 2025
Ward
St Andrews And Dockland
Case officer
Show
Decision
Application Permitted
Decision date
27 Feb 2026
Decision level
Committee Decision
Freehold owner
Show

How this decision compares

Decided in 253 days from validation, 171 days slower than Hull's median of 82 for full applications. Approved, as 92% of full applications here are.

34%decided within 8 weeks
92%approved
309decided in the last year

Plota live figures for full applications decided by Hull in the last twelve months, from validation. Hull decision record →

Public comments

No public comments yet.

134 neighbours consulted · Last counted 2 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14108508
Planning Portal ref
PP-14108508
Comments by
30 Jul 2025
Env. assessment
No
Hull
Planning Authority Score
2.6/10
Poor
#248 of 296 councils
Relevant to this application:
Change of use

Hull is slower than most councils at deciding householder applications, ranking #231 out of 296. The council extends the time limit on 62% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Frequently extends decision deadlines
expect longer than the statutory limit
These figures are council-wide context, not a prediction for this application. View full council performance
Hull decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #85 of 296
92%
Householder approved
Above avg (90%) #156 of 296
51%
Decided in 8 weeks
Below avg (63%) #231 of 296
62%
Extended time limit
Above avg (41%) #273 of 296
88%
Minor dwellings approved
16 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
88%
Change of use approved
33 decided
436
Total decisions
36 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Freehold owner: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.