Drainage Pond Norwich Main Substation Mangreen Hall Lane Dunston Norfolk Data via plota.co.uk

2025/2812 - Full Approved

Proposal

Installation of pre construction field drainage to support the operation of the Hornsea Project Three onshore export cable route (EIA Development) Data via plota.co.uk

View original council record ↗Last checked

Application progress

Received
8 Sept 2025
Validated
29 Jan 2026
Consultation
25 Jun 2026
Approved
28 Jul 2026

Approved on 28 Jul 2026 · Delegated · Last checked 1 Aug 2026

Documents 107

Statements & assessments 30

PDF Lead local flood authority Consultee Comment (D) · 8 Jul 2026 View ↗ PDF Ecology comments Consultee Comment (D) · 6 Jul 2026 View ↗ PDF Ecology comments Consultee Comment (D) · 6 Jul 2026 View ↗ PDF Updated design and access statement Report (K) · 24 Jun 2026 View ↗ PDF Applicant arboricultural response Report (K) · 10 Jun 2026 View ↗ PDF Ecology comments Consultee Comment (D) · 10 Jun 2026 View ↗ PDF Revised bng metric Report (K) · 10 Jun 2026 View ↗ PDF Bng statement Report (K) · 10 Jun 2026 View ↗ PDF Bng baseline map Report (K) · 10 Jun 2026 View ↗ PDF Ecology bng comments Consultee Comment (D) · 19 May 2026 View ↗ PDF Bng baseline map Drawing (K) · 14 May 2026 View ↗ PDF Lead local flood authority Consultee Comment (D) · 27 Apr 2026 View ↗ PDF Zone 74 1.05 bng metric Report (K) · 23 Mar 2026 View ↗ PDF Zone 74 1.03 bng metric Report (K) · 23 Mar 2026 View ↗ PDF Zone 71 bng metric Report (K) · 23 Mar 2026 View ↗ PDF Zone 61 bng metric Report (K) · 23 Mar 2026 View ↗ PDF Zone 60 bng metric Report (K) · 23 Mar 2026 View ↗ PDF Zone 29 bng metric Report (K) · 23 Mar 2026 View ↗ PDF Zone 20 bng metric Report (K) · 23 Mar 2026 View ↗ PDF 01-tcp Appendix 4 zone 74 drainage Drawing (K) · 18 Mar 2026 View ↗ PDF 02-tpp Appendix 5 zone 74 drainage Drawing (K) · 18 Mar 2026 View ↗ PDF Aia zone 74 drainage Report (K) · 18 Mar 2026 View ↗ PDF Heritage and design Consultee Comment (D) · 12 Feb 2026 View ↗ PDF Appendix 2 - design and access statement Report (K) · 23 Oct 2025 View ↗ PDF Bng small sites metric calculator Report (K) · 23 Oct 2025 View ↗ PDF Req 10 - ecological management plan Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 nc surface & foul water drainage Report (K) · 23 Oct 2025 View ↗ PDF Appendix 1 - drainage drawings Drawing (K) · 8 Sept 2025 View ↗ PDF Cover letter and eia assessment BackGround Papers (K) · 8 Sept 2025 View ↗ PDF Appendix 3 - ecology constraints assessment - tcpa drainage x1.05 Report (K) · 8 Sept 2025 View ↗

Consultation & comments 26

PDF Applicant response to llfa comments Report (K) · 24 Jun 2026 View ↗ PDF Landscape architect (snc) Consultee Comment (D) · 22 Apr 2026 View ↗ PDF Re-consultation instruction Officer Notes · 14 Apr 2026 View ↗ PDF Re-consultation instruction Officer Notes · 10 Apr 2026 View ↗ PDF Anglian water services ltd Consultee Comment (D) · 25 Mar 2026 View ↗ PDF Re-consultation email Correspondence (D) · 24 Mar 2026 View ↗ PDF Landscape architect (snc) Consultee Comment (D) · 23 Mar 2026 View ↗ PDF Re-consultation instruction Officer Notes · 18 Mar 2026 View ↗ PDF Environment agency Consultee Comment (D) · 11 Mar 2026 View ↗ PDF Anglian water Consultee Comment (D) · 11 Mar 2026 View ↗ PDF Ncc highways Consultee Comment (D) · 23 Feb 2026 View ↗ PDF Re-consultation instruction Officer Notes · 20 Feb 2026 View ↗ PDF Response to ea letter Correspondence (D) · 20 Feb 2026 View ↗ PDF Additional highway information re-consultation instruction Correspondence (D) · 20 Feb 2026 View ↗ PDF Historic england Consultee Comment (D) · 19 Feb 2026 View ↗ PDF Norwich international airport Consultee Comment (D) · 18 Feb 2026 View ↗ PDF Environment agency Consultee Comment (D) · 16 Feb 2026 View ↗ PDF Hse Consultee Comment (D) · 10 Feb 2026 View ↗ PDF Historic environment service Consultee Comment (D) · 9 Feb 2026 View ↗ PDF Natural england Consultee Comment (D) · 5 Feb 2026 View ↗ PDF The gardens trust Consultee Comment (D) · 5 Feb 2026 View ↗ PDF Landscape architect (snc) Consultee Comment (D) · 4 Feb 2026 View ↗ PDF Environmental quality Consultee Comment (D) · 2 Feb 2026 View ↗ PDF National gas Consultee Comment (D) · 30 Jan 2026 View ↗ PDF Llfa - extension of time request Consultee Comment (D) · 30 Jan 2026 View ↗ PDF Designing out crime officer Consultee Comment (D) · 30 Jan 2026 View ↗

Other documents 33

PDF Extension of time Correspondence (D) · 23 Jul 2026 View ↗ PDF Update cover letter Report (K) · 24 Jun 2026 View ↗ PDF Officer correspondence Correspondence (D) · 23 Mar 2026 View ↗ PDF Additional information rececived Correspondence (D) · 6 Feb 2026 View ↗ PDF Press advert BackGround Papers (K) · 5 Feb 2026 View ↗ PDF Request for information from ncc highways Correspondence (D) · 4 Feb 2026 View ↗ PDF Correspondence with agent re: invalid BackGround Papers (K) · 3 Nov 2025 View ↗ PDF Req 16- written scheme of investigation Report (K) · 23 Oct 2025 View ↗ PDF Req 17 - code of constuction practice - landfall & onshore cable corrider Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 surface and foul water drainange - appendix 1 - part 1 Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 surface and foul water drainange - appendix 1 - part 2 Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 surface and foul water drainange - appendix 1 - part 3 Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 surface and foul water drainange - appendix 1 - part 4 Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 surface and foul water drainange - appendix 1 - part 5 Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 surface and foul water drainange - appendix 1 - part 6 Report (K) · 23 Oct 2025 View ↗ PDF Req - 13 & 15 surface and foul water drainange - appendix 1 - part 7 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 1 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 12 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 11 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 16 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 14 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 17 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 16 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 2 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 13 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 3 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 5 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 4 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 6 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 7 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 8 Report (K) · 23 Oct 2025 View ↗ PDF Req 14 - contaminated land and groundwater - part 9 Report (K) · 23 Oct 2025 View ↗ PDF Form_1_cil_additional_information CIL Documentation (K) · 8 Sept 2025 View ↗

All documents on the council site ↗

Associated applications 2

Site constraints 3

Nutrient neutrality catchment: Yare Broads and Marshes
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Predicted from the national soil map. The older provisional map, which most planning maps still show, had this area as grade 3. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Habitat network: Network Expansion Zone
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 11 September 2026. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in South Norfolk Broadland - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full
Postcode
NR14 8PG
Received
8 Sept 2025
Validated
29 Jan 2026
Ward
Mulbarton And Stoke Holy Cross
Parish
Stoke Holy Cross
Case officer
Show
Decision
Approval with Conditions
Decision date
28 Jul 2026
Decision level
Delegated
Applicant
Show

How this decision compares

Decided in 180 days from validation, 131 days slower than South Norfolk Broadland's median of 49 for utility and infrastructure works. Approved, as 100% of utility and infrastructure works here are.

72%decided within 8 weeks
100%approved
55decided in the last year

Plota live figures for utility and infrastructure works decided by South Norfolk Broadland in the last twelve months, from validation. South Norfolk Broadland decision record →

Public comments

No public comments yet.

31 neighbours consulted · Last counted 1 Aug 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14313452
Neighbours
30 Jan 2026
Consultation
25 Jun 2026
Comments by
9 Jul 2026
Site or press notice
10 Feb 2026
Env. assessment
Yes
South Norfolk Broadland
Planning Authority Score
5.9/10
Average
#106 of 296 councils
Relevant to this application:
Householder decisions

South Norfolk Broadland ranks #136 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
South Norfolk Broadland decision statistics
Based on MHCLG data, the year to March 2026
93%
Overall approval rate
Above avg (87%) #50 of 296
95%
Householder approved
Above avg (90%) #71 of 296
67%
Decided in 8 weeks
Above avg (63%) #136 of 296
42%
Extended time limit
Above avg (41%) #161 of 296
82%
Minor dwellings approved
137 decided (1-9 homes)
92%
Major dwellings approved
12 decided (10+ homes)
100%
Change of use approved
33 decided
1,013
Total decisions
67 refused in the year to March 2026