Self-build home at The Greenway, Walberton
Summary of planning committee decision
Decided by Arun Planning Committee on 21 Oct 2026.
Earlier application
An earlier application for substantially the same development was withdrawn on 12 June 2026.
“WA/33/26/PLConstruction of a self-build/custom build single dwelling, with garage outbuilding and associated works. This is a departure from the local development plan and is in CIL Zone 3 and is CIL liable as a new dwelling. Withdrawn 12-06-26”
Officer report
Why officers supported it
Officers found policy conflict because of the site’s location and design, but gave greater weight to national policy supporting this infill and housing contribution.
“The site adjoins the BUAB as defined by the Walberton Neighbourhood Plan (WNP) which was made in 2021 and allocated sites for housing immediately to the west of the development site under WNP policy HP5. The WNP also allocated a site to the north of Gracelands Farm to the north of the site under WNP policy HP17. The site to the west has been completed, and the development site borders residential development on three sides.”
“NPPF policy S5 states that development which complies with one of the criteria should be approved, unless the benefits of doing so would be substantially outweighed by adverse effects. This is in favour of the proposal. NPPF Annexe A, paragraph 2 states that development plan policies which are materially inconsistent with national decision making policies within the NPPF should be given very limited weight.”
Officer report
What consultees said
Highways, ecology and environmental health raised no objection subject to conditions, while drainage engineers accepted the strategy subject to detailed approval.
“DRAINAGE ENGINEERS - No objection subject to conditions - Proposes a number of rainwater harvesting planters, with final discharge to soakaways. Re-use and infiltration to ground are the highest priority discharge methods, and the design accords with Standard 1 of the Non-Statutory SuDS Standards (NSfS). - Ground investigations demonstrate infiltration is viable, and is sufficient for planning stage to demonstrate feasibility of the strategy.”
“- There are a significant number of good quality trees on the site, most of which are to be retained. These existing trees are a constraint to the drainage strategy as any drainage installations should not damage the trees, and the drainage infrastructure itself needs to be protected from tree root damage. The design includes root protection construction over existing tree roots which can be progressed to technical design at discharge of conditions stage.”
Officer report
What people said
The parish council and nearby occupiers objected over drainage, trees, ownership, ecology, construction, flooding, backland development and privacy; one supporter welcomed the scheme.
“- Issues regarding land ownership, incorrect certificate and the applicants' right to access the land via the proposed access track and carry out works to this area. - Potential impact on dormice. - Discrepancy in site area as stated on the application form and drainage assessment, and impact on the proposed drainage strategy. - Impact on trees. - Disruption during construction. - Impact on drainage and flooding. - Backland development.”
Officer report
What members debated
Members discussed ownership, the site area, biodiversity exemption, drainage, groundwater, tree removal and safeguards against pile driving.
“Concerns were raised regarding the previous removal of trees from the site and the potential loss of biodiversity. Questions were also asked about the site's drainage strategy, given the area’s known groundwater conditions and history of flooding. In response, Members were advised that the proposed surface water strategy relied upon infiltration and that all runoff from the development would be managed within the site.”
“Further concern was expressed regarding the site's location above a major aquifer and the potential risks associated with pile driving. Members queried whether additional safeguards could be provided to protect groundwater resources. Following discussion, a proposal by Councillor Wallsgrove was made and seconded by Councillor Bence to add a condition preventing pile driving on the site.”
Minutes
The decision
The committee delegated authority to grant permission, subject to the reported conditions, a self-build legal agreement and resolution of the ownership certificate issue.
“Following consideration of the matters raised, Members proceeded to determine the application on the officer recommendation, as amended to include the additional condition preventing pile driving, and subject to the completion of the self-build legal agreement and resolution of the ownership certificate issue.”
“That it delegates the decision to the Group Head of Planning, with authority to grant permission subject to the conditions and informatives as set out in the report and subject to the satisfactory completion of a legal agreement to secure the proposed dwelling as self-build.”
Minutes
Councillors at the meeting
- Sue WallsgroveChairVice-Chair, in the chairGreenFor(no vote against recorded)
- Bob WoodmanChairLib DemFor(no vote against recorded)
- Trevor BenceReform UKFor(no vote against recorded)
- Richard BowerConservativeFor(no vote against recorded)
- Billy Blanchard-CooperLib DemFor(no vote against recorded)
- June HamiltonIndependentFor(no vote against recorded)
- Paul KellyConservativeFor(no vote against recorded)
- Martin LuryLib DemFor(no vote against recorded)
- Mike NortheastLabourFor(no vote against recorded)
- George O'NeillSubstitute for McDougallLabourFor(no vote against recorded)
- Mark TurnerSubstitute for PartridgeConservativeFor(no vote against recorded)
The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.
Proposed by Councillor Bob Woodman, seconded by Councillor Mike Northeast.
Apologies Simon McDougall Labour, Peggy Partridge Conservative
Also attending Carol Birch Green, Shaun Gunner Conservative, Mel Penycate Green
Source: Plota analysis of the council's minutes; parties from the council's list of councillors.
Sources
- Arun Planning Committee minutes, 21 October 2026
- Agenda and papers (council website)
Source: Plota analysis of Arun's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Arun Planning Committee
- Council
- Arun
- Date
- Wednesday 21 October 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Councillors
- 11Conservative 3Lib Dem 3Labour 2Green 1Independent 1Reform UK 1Show votes
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Arun committee decisions →
This committee's year
63 decisions in the 12 months to this meeting, 7 against officer advice.
Source: Plota analysis of the committee's minutes.