Land At Byley Road Byley Northwich Data via plota.co.uk

26/03070/FUL - Full Application Awaiting decision

Proposal

Construction of two warehouse/industrial buildings; a fork lit truck charging station; service yard and associated landscaping including wild life ponds Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
25 Sept 2026
✓
Validated
2 Nov 2026
Decision
Expected by 28 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 27 Dec 2026 and 31 Jan 2027, from Chester's recent commercial and major works.

Comments are open until 26 Nov 2026

Comment on this application ↗

Site constraints 2

Agricultural land, grade 4
Poor quality farmland, not best and most versatile. Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 3. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 48 m away: Keuper Gas Storage Project
The site is 48 m from the project boundary. Underground gas storage, decided. The project page says whether consent was granted. Also within 2 km: Keuper Underground Gas Storage Facility Material Change 1 (at pre-application, 49 m); Peak Cluster CCS Pipeline (at pre-application, 837 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 3 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Looking for land for a warehouse?

Plota Sites searches every land parcel in England and Wales: 11,482 sites fit this search. On and off the market, free to search.

Land for big warehouses
Work with planning data?

Every application in Chester - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Chester
Application type
Full Application
Postcode
CW10 9NT
Received
25 Sept 2026
Validated
2 Nov 2026
Ward
Shakerley
Parish
Byley
Applicant
Show

Decision outlook

Day 21 of the 56-day target. Chester usually decides commercial and major works by day 69.

Day 2148 days to the predicted decision (day 69)
41%decided within 8 weeks
94%approved
36decided in the last year

Plota live figures for commercial and major works decided by Chester in the last twelve months, from validation. Chester decision record →

Public comments

No public comments yet.

8 neighbours consulted · Last counted 17 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15241187
Planning Portal ref
PP-15241187
Comments by
26 Nov 2026
Env. assessment
No