Grove End Edgehill Data via plota.co.uk

26/02373/ELECPD - Electricity Works Permitted Development Pending Consideration

Proposal

Replace existing transformer pole (like for like) and replace existing transformer (box) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
21 Sept 2026
Decision
Expected by 19 Oct 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 11 Nov 2026 and 22 Nov 2026, from Stratford on Avon's recent utility and infrastructure works.

The consultation period closed on 2 Oct 2026.

Site constraints 5

Cotswolds National Landscape
Great weight to conserving the landscape; major development restricted.
Previously an area of outstanding natural beauty, which is still the designation in law. Since 2023 authorities must seek to further its purpose, not merely have regard to it.
Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 4. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Radon affected area, class 6
An estimated 30% or more of homes reach the radon action level. Indicative for the 1 km square, which takes the highest class found in it; a radon test gives the answer for a building.
From the British Geological Survey and UK Health Security Agency indicative atlas. Under building regulations, as the BRE guide BR 211 (2023) sets out, new buildings and extensions need basic radon protection from class 3 in England and Wales and from class 2 in Scotland, and full protection from class 5. The class at the site itself, from the detailed BGS map, decides which.
UKHSA radon ↗
Registered park or garden 69 m away: Radway Grange
Its setting is a consideration for work nearby.
Registered parks and gardens, battlefields, world heritage sites and protected wrecks are designated heritage assets: harm needs clear and convincing justification.
Historic England ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area206 m² (2,217 sq ft)
Energy ratingA (asset rating 16)
UseB1 Offices and Workshop businesses
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in August 2021, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Stratford on Avon - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Electricity Works Permitted Development
Received
21 Sept 2026
Validated
21 Sept 2026
Ward
Tysoe
Parish
Ratley & Upton
Case officer
Show
Target decision
19 Oct 2026
Applicant
Show

Decision outlook

Day 18 of the 56-day target. Stratford on Avon usually decides utility and infrastructure works by day 59.

Day 1841 days to the predicted decision (day 59)
48%decided within 8 weeks
93%approved
68decided in the last year

Plota live figures for utility and infrastructure works decided by Stratford on Avon in the last twelve months, from validation. Stratford on Avon decision record →

Consultation & key dates

Consultation
2 Oct 2026
Comments by
2 Oct 2026
Stratford on Avon
Planning Authority Score
5.5/10
Average
#121 of 296 councils
Relevant to this application:
Householder decisions

Stratford on Avon ranks #142 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Stratford on Avon decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #94 of 296
95%
Householder approved
Above avg (90%) #93 of 296
67%
Decided in 8 weeks
Above avg (63%) #142 of 296
42%
Extended time limit
Above avg (41%) #166 of 296
82%
Minor dwellings approved
146 decided (1-9 homes)
91%
Major dwellings approved
11 decided (10+ homes)
87%
Change of use approved
53 decided
1,257
Total decisions
98 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.