The Ferry Terminal Colintraive Argyll And Bute PA22 3AP Data via plota.co.uk

25/02132/PP - Planning Permission Approved

Proposal

Erection of SSEN Substation and LV Switchgear room. Installation of 6 subsurface cable ducts and installation of a shore power arm to enable ferry charging Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Dec 2025
✓
Validated
2 Feb 2026
✓
Consultation
10 Feb 2026
✓
Approved
27 Mar 2026

Approved on 27 Mar 2026 · Local Delegated Decision · Last checked 6 Jul 2026

Associated applications 3

Site constraints 1

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Not affected
No listed building at the site · No scheduled monument at the site

Checked on 3 November 2026. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Argyll - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Argyll
Application type
Planning Permission
Postcode
PA22 3AP
Received
22 Dec 2025
Validated
2 Feb 2026
Ward
Cowal
Parish
Colintraive And Glendaruel CC
Case officer
Show
Target decision
1 Apr 2026
Decision
Application Approved
Decision date
27 Mar 2026
Decision level
Local Delegated Decision
Applicant
Show
Agent
Evonne Maxwell

How this decision compares

Decided in 53 days from validation, about the council's usual 55 days. Approved, as 99% of utility and infrastructure works here are.

54%decided within 8 weeks
99%approved
203decided in the last year

Plota live figures for utility and infrastructure works decided by Argyll in the last twelve months, from validation. Argyll decision record →

Consultation & key dates

Alt. reference
100738114-001
Consultation
10 Feb 2026
Comments by
6 Mar 2026
Site or press notice
13 Feb 2026
Statutory expiry
1 Apr 2026
Env. assessment
No