Roof extension, nine homes at Theatre Building, Bow, London E3

Summary of planning committee decision

Decided by Tower Hamlets Development Committee on 1 Sept 2026.

PA/25/01155/A1Approved

No officer report was published for this decision; this summary is from the committee minutes.

A two-storey roof extension

The scheme would add a two-storey roof extension to the Theatre Building to provide nine dwellings, with cycle parking, refuse storage and landscaping.

“Paul Buckenham (PB) introduced the report relating to a development to provide a two-storey roof extension to the existing Theatre Building, 1 Paton Close, comprising nine dwellings, associated cycle parking, access, refuse and recycling storage, amenity space, landscaping, and restoration works to the existing façade of the Theatre Building.”

Minutes

Officers recommended approval

Officers recommended granting permission, saying the scheme preserved the conservation area, met space and amenity standards, and would be car-free.

“Following the introduction, Katie Cooke (KC), Planning Case Officer, presented the details of the scheme. She explained that it remained broadly unchanged from an earlier application and was considered to preserve the character of the Fairfield Road Conservation Area and nearby heritage assets. The proposed units met space standards, with acceptable daylight, sunlight and residential amenity impacts.”

“S106 obligations and conditions. Officers then recommended granting planning permission.”

Minutes

Objectors raised access and safety concerns

Objectors raised concerns about bin storage, cycle access, structural impacts of adding two storeys and management of the additional homes.

“The Committee heard from an objector who raised concerns about the building’s existing inadequate bin storage, questioning whether the proposed additional bins could be practically accessed and collected and whether this could realistically be resolved by condition.”

“A second objector was heard who expressed concerns about the structural capacity and construction impacts of adding two storeys, including disruption to existing residents and potential loss of lift access. Concerns were also raised about the inadequacy of the proposed bin and cycle storage, the impact on residential amenity and the lack of clarity over management arrangements for the additional homes.”

Minutes

The applicant's representative spoke in support

The applicant's representative said the proposal matched a previously approved scheme and supported housing delivery.

Members questioned heritage and safety

Members asked about heritage impacts, cycle access, fire and cladding safety, and why there was no affordable housing, and officers responded.

“Clarification was sought on fire safety, building safety and sprinkler provision. Officers confirmed that the proposal had been subject to consultation from the Building Safety Regulator and that the required fire statement had been accepted. Sprinklers formed part of the fire safety measures, with detailed…”

“Members queried why the scheme comprised only nine dwellings, especially as this fell below the threshold for affordable housing provision. Officers advised that the number of units was determined by the required building massing, setbacks and amenity space provision, with the available space being maximised. They also noted that given the small site, the applicant has agreed to a contribution towards affordable housing.”

Minutes

Committee voted to grant permission

The committee voted 4 in favour and 1 against to grant permission, with one councillor objecting over the lack of affordable housing.

“Re PA/25/01155, the Committee voted 4 in favour, 1 against and 0 abstentions.”

“It was noted that Councillor Mads Churchhouse objected to the scheme due to the lack of affordable housing provision, noting that the application would have been more acceptable if it had included affordable housing in line with the Local Plan and Policy DH2.”

Minutes

Permission granted

Planning permission was granted subject to conditions and a Section 106 agreement.

“That planning permission for PA/25/01155, Theatre Building, 1 Paton Close, London, E3 be GRANTED subject to conditions and a Section 106 Agreement, as set out in the main report and update report.”

Minutes

Councillors at the meeting

Apologies Abu Talha Chowdhury Aspire

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Tower Hamlets Development Committee minutes, 1 September 2026
  • Agenda and papers (council website)

Source: Plota analysis of Tower Hamlets's committee minutes. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Tuesday 1 September 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Vote
4 for, 1 against
Councillors
5Aspire 4Green 1Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

Source: Plota analysis of the minutes.

This committee's year

9 decisions in the 12 months to this meeting, 1 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →