57 & 59 Ashley Road, New Milton BH25 6AZ (Nb: Subject to Unilateral Undertaking) Data via plota.co.uk

25/10969 - Full Planning Permission Approved

Proposal

Side & rear extensions to form maisonette. Removal of existing garage. Fenestration alterations, external staircase, and parking. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Oct 2025
✓
Validated
10 Nov 2025
✓
Consultation
12 Nov 2025
✓
Approved
12 Mar 2026

Approved on 12 Mar 2026 · Development Control Committee · Last checked 10 Oct 2026

Planning committee

Decided by New Forest (District) Planning Committee on 11 Mar 2026.

Approved

As officers recommended.

  • Officers advised approval because the proposal’s benefits outweighed its minor harms, subject to conditions and a legal agreement.
  • Three representations supported the housing, while three raised concerns about design, residential amenity and parking.
  • The committee granted permission subject to conditions.

Source: Plota analysis of New Forest (District)'s committee minutes, New Forest (District) Planning Committee minutes, 11 March 2026 .

Documents 27

Other documents 12

PDF CIL LIABILITY NOTICE Obligation Correspondence · 16 Mar 2026 View ↗ PDF OFFICERS REPORT Reports · 4 Mar 2026 View ↗ PDF DRAFT UNILATERAL UNDERTAKING Legal Agreements · 18 Feb 2026 View ↗ PDF Granted_PRA Submitted Applications · 22 Dec 2025 View ↗
PDF Commenter’s name hidden Show Representees · 15 Dec 2025 View ↗
PDF Commenter’s name hidden Show Representees · 12 Dec 2025 View ↗
PDF Commenter’s name hidden Show Representees · 4 Dec 2025 View ↗
PDF Commenter’s name hidden Show Representees · 4 Dec 2025 View ↗
PDF Commenter’s name hidden Show Representees · 3 Dec 2025 View ↗
PDF Commenter’s name hidden Show Representees · 1 Dec 2025 View ↗
PDF Granted_HIGH SPEED BROADBAND Submitted Applications · 4 Nov 2025 View ↗ PDF Granted_WATER QUALITY CHECKLIST Submitted Applications · 4 Nov 2025 View ↗

All documents on the council site ↗

Site constraints 5

Nutrient neutrality catchment: Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
National infrastructure project: Navitus Bay Wind Park
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
1 listed building within 150 m
Nearest: Ashley Arnewood, Grade II, 46 m away
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Historic England ↗
Also on the record
Radon affected area, class 3; Inside the New Milton built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area144 m² (1,550 sq ft)
Energy ratingD (67 out of 100), could reach C
PropertyDetached flat, 5 habitable rooms
Built1950 to 1966
HeatingBoiler and radiators, mains gas
WallsCavity wall, filled cavity

From the energy performance certificate lodged in October 2009, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in New Forest (District) - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
BH25 6AZ
Received
28 Oct 2025
Validated
10 Nov 2025
Ward
Milton
Parish
New Milton
Case officer
Show
Target decision
13 Mar 2026
Decision
Granted Subject to Conditions
Decision date
12 Mar 2026
Decision level
Development Control Committee
Applicant
Show

How this decision compares

Decided in 122 days from validation, 69 days slower than New Forest (District)'s median of 53 for full applications. Approved, as 92% of full applications here are.

67%decided within 8 weeks
92%approved
746decided in the last year

Plota live figures for full applications decided by New Forest (District) in the last twelve months, from validation. New Forest (District) decision record →

Public comments

6comments received
3 objecting3 supporting

50% support · above the UK average of 16%

10 neighbours consulted · Last counted 10 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Consultation
12 Nov 2025
Comments by
12 Dec 2025
Committee
11 Mar 2026
Env. assessment
No
New Forest (District)
Planning Authority Score
7.8/10
Good
#29 of 296 councils
Relevant to this application:
Householder decisions

New Forest (District) is faster than most councils at deciding householder applications, ranking #37 out of 296. Householder applications are slightly more likely to be approved here (96%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
New Forest (District) decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #112 of 296
96%
Householder approved
Above avg (90%) #54 of 296
80%
Decided in 8 weeks
Above avg (63%) #37 of 296
35%
Extended time limit
Below avg (41%) #103 of 296
69%
Minor dwellings approved
87 decided (1-9 homes)
91%
Major dwellings approved
11 decided (10+ homes)
78%
Change of use approved
40 decided
885
Total decisions
85 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.