What was proposed

The application proposed a synthetic turf pitch with fencing, floodlights, parking, access routes, storage and a relocated discus cage.

“The Committee considered a proposal that sought permission for the construction of a synthetic turf pitch and associated sports and transport infrastructure to support both school curriculum activities and community use outside school hours.”

“The proposed development included: • Construction of a synthetic turf pitch measuring approximately 91m x 55m; • Installation of 4.5m high weld-mesh perimeter security fencing with noise-damping fixings, incorporating a 1.1m high internal spectator barrier; • Installation of six 15m high floodlighting columns fitted with directional LED luminaires providing up to 200 lux illumination, with the ability to dim to 120 lux; • Provision of a dedicated maintenance and equipment…”

Minutes

The site and operation

The amended operating hours were weekday mornings to evenings and daytime hours at weekends and on Bank Holidays.

“Members noted the following amendments to the scheme, the proposed operational hours for the pitch and floodlighting were: • 9.00am to 9.30pm Monday to Friday; • 9.00am to 6.00pm on Saturdays; and • 9.00am to 6.00pm on Sundays and Bank Holidays.”

Minutes

What officers recommended

Officers considered the impacts acceptable with conditions and concluded that the educational and community benefits outweighed limited, manageable impacts.

“The officer reported that the design and visual impacts were considered acceptable, subject to landscaping and mitigation measures. Potential impacts relating to noise, lighting, vehicle movements, drainage and microplastic containment had been assessed by relevant consultees and were considered acceptable subject to planning conditions, including restrictions on operating hours, noise management measures and drainage controls.”

“The officer concluded that the educational and community benefits of the development were significant and, on balance, outweighed the limited and mitigable impacts identified. Officers therefore recommended that planning permission be granted.”

Minutes

What people said

An objector and a councillor raised concerns about nearby homes, noise, lighting, drainage, flooding, disturbance and enforcement, while the applicant described community benefits.

What members debated

Members questioned drainage, lighting and noise controls, and officers proposed stronger requirements for implementation, secondary lighting and site-wide noise management.

“During general debate Members sought clarification on the proposed drainage, lighting and noise mitigation measures. Officers advised that Condition 13 was proposed to be amended to strengthen drainage requirements relating to drainage channels and pipework. Further amendments were also proposed to Conditions 6 and 9 to ensure that the approved schemes were implemented in full.”

“Members also discussed the impact of pathway lighting and whether illumination levels should be controlled in a similar manner to the car park lighting. Officers advised that the applicant would be required to comply with the approved lighting specifications, while legal advice confirmed that additional conditions controlling secondary site lighting and its hours of operation could be imposed if considered necessary.”

Minutes

The vote

The resolution passed with one vote in favour, no votes against and three abstentions.

“The vote for the resolution to grant planning permission was granted by one vote in favour with no objections and 3 abstentions. Councillor Gary Payne voted in favour. Councillors Sathya Maddasani, Russell Smith and Iurie Bivol abstained from voting.”

Minutes

The decision

Planning permission was granted subject to the officer conditions and amendments covering drainage, lighting and a site-wide Noise Management Plan.

“Following discussion and consideration of the application, the Committee resolved that planning permission be Granted, subject to the conditions set out in the officer's report, amended conditions relating to drainage and implementation of approved schemes, an additional condition controlling secondary site lighting and its hours of operation and a requirement that the Noise Management Plan applies to the entire site including the pitch, spectator areas, pedestrian access…”

Minutes

Councillors at the meeting

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Havering Planning Committee (until October 2026) minutes, 29 October 2026
  • Agenda and papers (council website)

Source: Plota analysis of Havering's committee minutes. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Havering
Date
Thursday 29 October 2026
Committee decided
Approved
Councillors
4Reform UK 4Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)