Land North Of Stevens And Carlotti Ramsgate Road Sandwich CT13 9NL Data via plota.co.uk

25/01399 - Screening Opinion Decided

Proposal

EIA Screening Opinion - Construction and Operation of a Greener Grid Park Comprising Synchronous Compensators, Transformers, Ancillary Plant, Underground Electricity Ducting and Cabling to Connect to Existing Substation and Associated Hard and Soft Landscaping Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
23 Dec 2025
✓
Validated
24 Dec 2025
✓
EIA Not Required
19 Feb 2026

EIA Not Required on 19 Feb 2026 · Delegated · Last checked 3 Oct 2026

Site constraints 7

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
National infrastructure project 76 m away: Richborough Connection Project
The site is 76 m from the project boundary. Electricity line, decided. The project page says whether consent was granted. Also within 2 km: Thanet Extension Offshore Wind Farm (decided, 76 m); Sea Link (awaiting the Secretary of State's decision, 809 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Special protection area 325 m away: Thanet Coast & Sandwich Bay; SSSI 325 m away: Sandwich Bay to Hacklinge Marshes SSSI; Coalfield, development low risk area; Inside the Cliffs End built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Dover - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Dover
Application type
Screening Opinion
Postcode
CT13 9NL
Received
23 Dec 2025
Validated
24 Dec 2025
Ward
Sandwich
Parish
SANDWICH
Case officer
Show
Target decision
18 Feb 2026
Decision
EIA Not Required
Decision date
19 Feb 2026
Decision level
Delegated
Applicant
Show
Agent
Tetra Tech

Public comments

No public comments yet.

Last counted 3 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
14 Jan 2026
Env. assessment
No
Dover
Planning Authority Score
7.4/10
Good
#46 of 296 councils
Relevant to this application:
Householder decisions

Dover is one of the fastest councils in England for householder decisions, ranking #28 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Dover decision statistics
Based on MHCLG data, the year to March 2026
88%
Overall approval rate
Above avg (87%) #151 of 296
92%
Householder approved
Above avg (90%) #151 of 296
83%
Decided in 8 weeks
Above avg (63%) #28 of 296
31%
Extended time limit
Below avg (41%) #57 of 296
72%
Minor dwellings approved
105 decided (1-9 homes)
83%
Major dwellings approved
18 decided (10+ homes)
82%
Change of use approved
56 decided
772
Total decisions
89 refused in the year to March 2026