Longannet Power Station Alloa Fife FK10 4AA Data via plota.co.uk

26/02753/FULL - Full Planning Permission Registered

Proposal

Erection of cable sealing end (CSE) compound, raised platform, access road, fencing and associated infrastructure. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
13 Oct 2026
Decision
Expected by 8 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision soon after comments close on 3 Dec 2026, from Fife's recent utility and infrastructure works.

Comments are open until 3 Dec 2026

Comment on this application ↗

Documents 21

All documents on the council site ↗

Site constraints 4

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Also on the record
Local nature reserve 466 m away: Firth of Forth; Coalfield, development low risk area; SSSI 466 m away: Firth of Forth.
Not affected
No listed building at the site · No scheduled monument at the site

Checked on 6 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Fife - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Fife
Application type
Full Planning Permission
Postcode
FK10 4AA
Received
13 Oct 2026
Validated
13 Oct 2026
Ward
West Fife And Coastal Villages
Parish
Kincardine
Case officer
Show
Applicant
Show
Agent
SP Energy Networks

Decision outlook

Day 36 of the 56-day target. Fife usually decides utility and infrastructure works by day 38.

Day 3620 days to the 56-day target
78%decided within 8 weeks
68%approved
309decided in the last year

Plota live figures for utility and infrastructure works decided by Fife in the last twelve months, from validation. Fife decision record →

Consultation & key dates

Alt. reference
100764123-001
Comments by
3 Dec 2026
Env. assessment
No