Halebourne Cottage Halebourne Lane Chobham Woking Surrey GU24 8SL Data via plota.co.uk

26/0076/FFU - Full Planning Application Approved

Proposal

Erection of a self build dwelling following demolition of the existing dwelling. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Jan 2026
✓
Validated
16 Feb 2026
✓
Consultation
4 Mar 2026
✓
Approved
13 Apr 2026

Approved on 13 Apr 2026 · Delegated Decision · Last checked 1 Aug 2026

Documents 35

All documents on the council site ↗

Associated applications 3

Site constraints 4

Green belt: London
Inappropriate development needs very special circumstances.
Green belt policy allows a short list of exceptions, such as limited extensions and replacement buildings. Anything else needs very special circumstances that clearly outweigh the harm. Some green belt land can count as grey belt, where it does not strongly serve the green belt's purposes. The council decides this in its green belt assessment or on each application, so we do not mark it here.
Read the government guidance ↗
Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 4. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 278 m away: Southampton to London Pipeline Project
The site is 278 m from the project boundary. Pipeline, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Not affected
Outside flood zones 2 and 3 · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £2,500,000 in January 2025. Other property, freehold.

6 January 2025£2,500,000Recorded as a transfer outside a standard sale

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area219 m² (2,357 sq ft)
Energy ratingE (44 out of 100)
PropertyDetached house, 7 habitable rooms
Built1996 to 2002
HeatingBoiler and underfloor heating, LPG, Boiler and radiators, LPG
WallsCavity wall, as built, insulated (assumed)

From the energy performance certificate lodged in June 2024, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Surrey Heath - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Application
Postcode
GU24 8SL
Received
28 Jan 2026
Validated
16 Feb 2026
Ward
Bisley & West End
Parish
Chobham Parish Council
Case officer
Show
Target decision
13 Apr 2026
Decision
Grant
Decision date
13 Apr 2026
Decision level
Delegated Decision
Applicant
Show
Agent
Paul Dickinson and Associates

How this decision compares

Decided in 56 days from validation, about the council's usual 55 days. Approved, as 80% of demolitions here are.

74%decided within 8 weeks
80%approved
90decided in the last year

Plota live figures for demolitions decided by Surrey Heath in the last twelve months, from validation. Surrey Heath decision record →

Public comments

No public comments yet.

2 neighbours consulted · Last counted 1 Aug 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14622414
Planning Portal ref
PP-14622414
Neighbours
17 Feb 2026
Consultation
4 Mar 2026
Comments by
3 Apr 2026
Site or press notice
6 Mar 2026
Statutory expiry
13 Apr 2026
Env. assessment
No
Surrey Heath
Planning Authority Score
4.8/10
Below average
#163 of 296 councils
Relevant to this application:
Householder decisions

Surrey Heath ranks #134 out of 296 councils for householder decision speed. Householder applications are slightly less likely to be approved here (87%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Surrey Heath decision statistics
Based on MHCLG data, the year to March 2026
87%
Overall approval rate
Above avg (87%) #182 of 296
87%
Householder approved
Below avg (90%) #235 of 296
68%
Decided in 8 weeks
Above avg (63%) #134 of 296
34%
Extended time limit
Below avg (41%) #94 of 296
74%
Minor dwellings approved
39 decided (1-9 homes)
86%
Major dwellings approved
7 decided (10+ homes)
95%
Change of use approved
20 decided
600
Total decisions
78 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.