145 Prince Albert Road Southsea PO4 8EL Data via plota.co.uk

25/01515/FUL - Full Application Approved

Proposal

Change of use from dwellinghouse (Class C3) to purposes falling within dwellinghouse (Class C3) or house in multiple occupation (Class C4) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
23 Dec 2025
✓
Validated
24 Dec 2025
✓
Consultation
6 Jan 2026
✓
Approved
26 Feb 2026

Approved on 26 Feb 2026 · Fully Delegated Decision · Last checked 3 Oct 2026

Planning committee

Decided by Portsmouth Planning Committee on 25 Feb 2026.

Approved

As officers recommended.

  • Officers advised permission because the proposal met housing, amenity, parking and other planning requirements.
  • Seven representations objected, citing HMOs, parking, character, noise, services, crime, accommodation and the policy threshold.
  • The committee granted permission subject to three conditions after members considered the requirements met.
Read how the committee decided The proposal, site, officers’ assessment, objections, speakers, committee debate, vote and conditions. Includes the meeting recording, from 5:08:38 where this application was taken

Source: Plota analysis of Portsmouth's committee minutes of 25 Feb 2026.

Site constraints 4

Nutrient neutrality catchment: Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
National infrastructure project 662 m away: AQUIND Interconnector
The site is 662 m from the project boundary. Electricity line, awaiting the Secretary of State's decision. Also within 2 km: Hampshire Water Transfer and Water Recycling Project (accepted for examination, 846 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Portsmouth built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £60,000 in June 1998. Terraced house, freehold.

24 June 1998£60,000

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area174 m² (1,873 sq ft)
Energy ratingC (72 out of 100), could reach B
PropertyMid-terrace house, 7 habitable rooms
Built1900 to 1929
HeatingBoiler and radiators, mains gas
WallsCavity wall, as built, no insulation (assumed)

From the energy performance certificate lodged in May 2026, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Portsmouth - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Portsmouth
Application type
Full Application
Postcode
PO4 8EL
Received
23 Dec 2025
Validated
24 Dec 2025
Ward
Milton
Case officer
Show
Target decision
2 Mar 2026
Decision
Conditional Permission
Decision date
26 Feb 2026
Decision level
Fully Delegated Decision
Applicant
Show
Agent
Applecore PDM

How this decision compares

Decided in 64 days from validation, 14 days faster than Portsmouth's median of 78 for full applications. Approved, as 76% of full applications here are.

36%decided within 8 weeks
76%approved
17%go to committee

Plota live figures for full applications decided by Portsmouth in the last twelve months, from validation. Portsmouth decision record →

Public comments

8comments received
7 objecting1 neutral

88% object · above the UK average of 74%

7 neighbours consulted · Last counted 3 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14584038
Planning Portal ref
PP-14584038
Neighbours
6 Jan 2026
Consultation
6 Jan 2026
Comments by
3 Feb 2026
Site or press notice
7 Jan 2026
Committee
25 Feb 2026
Statutory expiry
18 Feb 2026
Env. assessment
No
Portsmouth
Planning Authority Score
3.1/10
Poor
#232 of 296 councils
Relevant to this application:
Change of use

Portsmouth ranks #188 out of 296 councils for householder decision speed. 48% of applications have the time limit extended, above the 41% national average. Householder applications are slightly less likely to be approved here (89%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Portsmouth decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #196 of 296
89%
Householder approved
Below avg (90%) #207 of 296
60%
Decided in 8 weeks
Below avg (63%) #188 of 296
48%
Extended time limit
Above avg (41%) #217 of 296
61%
Minor dwellings approved
44 decided (1-9 homes)
90%
Major dwellings approved
10 decided (10+ homes)
77%
Change of use approved
99 decided
613
Total decisions
85 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.