GLENSIDE, 45 Windmill Lane, Alton, Hampshire, GU34 2SN Data via plota.co.uk

EHDC-25-1093-FUL - Full Planning Application Approved

Proposal

The erection of a new 1.5 storey dwelling on land to the east of 45 Windmill Lane Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
15 Sept 2025
✓
Validated
26 Sept 2025
✓
Approved
27 Jan 2026

Approved on 27 Jan 2026 · Committee · Last checked 18 Oct 2026

Planning committee

Decided by East Hampshire Planning Committee on 22 Jan 2026.

Approved

No officer report was published for this decision; this summary is from the committee minutes.

  • Permission was granted for the new house, subject to a set of planning conditions.
  • Conditions required a drainage scheme to be agreed before work started and porous surfaces to stop run-off reaching the highway.
  • A condition removed permitted development rights, so no extensions can be added to the house without further planning permission.
Read how the committee decided The conditions attached to the new house, including tree and drainage requirements.

Source: Plota analysis of East Hampshire's committee minutes of 22 Jan 2026.

Documents 22

All documents on the council site ↗

Site constraints 5

Priority habitat: No main habitat but additional habitats present
A habitat of principal importance. It shapes the ecology work and the biodiversity net gain a scheme has to show.
Radon affected area, class 5
An estimated 10 to 30% of homes reach the radon action level. Indicative for the 1 km square, which takes the highest class found in it; a radon test gives the answer for a building.
From the British Geological Survey and UK Health Security Agency indicative atlas. Under building regulations, as the BRE guide BR 211 (2023) sets out, new buildings and extensions need basic radon protection from class 3 in England and Wales and from class 2 in Scotland, and full protection from class 5. The class at the site itself, from the detailed BGS map, decides which.
UKHSA radon ↗
National infrastructure project 928 m away: Southampton to London Pipeline Project
The site is 928 m from the project boundary. Pipeline, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Alton (East Hampshire) built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £225,000 in April 2006. Detached house, freehold.

28 April 2006£225,000

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area89 m² (958 sq ft)
Energy ratingB (89 out of 100), could reach A
PropertyDetached bungalow, 4 habitable rooms
Built1950 to 1966
HeatingBoiler and radiators, mains gas
WallsCavity wall, filled cavity

From the energy performance certificate lodged in March 2025, the latest held for this property, matched to this application by its address. The building may have changed since. View the certificate

Work with planning data?

Every application in East Hampshire - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Application
Postcode
GU34 2SN
Received
15 Sept 2025
Validated
26 Sept 2025
Ward
Alton Ashdell
Parish
Alton CP
Case officer
Show
Target decision
21 Nov 2025
Decision
Permission
Decision date
27 Jan 2026
Decision level
Committee
Applicant
Show
Agent
Voller Architectural Design

How this decision compares

Decided in 123 days from validation, 33 days faster than East Hampshire's median of 156 for new homes. Approved, as 69% of new homes here are.

14%decided within 8 weeks
69%approved
9%go to committee

Plota live figures for new homes decided by East Hampshire in the last twelve months, from validation. East Hampshire decision record →

Consultation & key dates

Comments by
19 Oct 2025
Statutory expiry
21 Nov 2025
East Hampshire
Planning Authority Score
1.5/10
Poor
#282 of 296 overall
Relevant to this application:
Householder decisions

East Hampshire is one of the slowest councils in England for householder decisions: #293 of 296 on speed. The council extends the time limit on 72% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly more likely to be approved here (91%) than the national average (90%).

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
East Hampshire decision statistics
Based on MHCLG data, the year to March 2026
88%
Overall approval rate
Above avg (87%) #153 of 296
91%
Householder approved
Above avg (90%) #173 of 296
24%
Decided in 8 weeks
Below avg (63%) #293 of 296
72%
Extended time limit
Above avg (41%) #288 of 296
63%
Minor dwellings approved
72 decided (1-9 homes)
78%
Major dwellings approved
9 decided (10+ homes)
88%
Change of use approved
24 decided
606
Total decisions
72 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.