Mobile Mini Ltd, Access Roads in Disused Airfield, North Killingholme, Immingham, DN40 3JY Data via plota.co.uk

PA/2026/416 - Full planning permission Pending

Proposal

Planning permission for the storage and processing of petroleum coke and associated 3m high earth bund wall topped with 1m high netted fence to entire perimeter. New concrete hardstanding, shelter building for storage of screened material, new drainage channel feeding into settlement and storage tanks, dust suppression system, wheel washing system, new lighting and welfare cabins and associated vehicle parking - AMENDED DESCRIPTION - Update surface water drainage details to proposing a revised strategy for the site to operate as a non-discharge site, resulting in no surface water discharge from the site Amended updated drainage details, Phase 1 desk study, palisade fencing, concrete joint layout, storage with water main details and duct layout, sections through the bunds and planning statement Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
5 Jun 2026
Decision
Expected by 31 Jul 2026

Under consideration

No decision has been issued yet. Plota predicted a decision soon after comments close on 23 Oct 2026; it is now day 126.

Comments are open until 23 Oct 2026

Comment on this application ↗

Site constraints 3

National infrastructure project 916 m away: VPI Immingham OCGT
The site is 916 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Hornsea Offshore Wind Farm (Zone 4) - Project Two (decided, 1190 m); Hornsea Offshore Wind Farm (Zone 4) - Project One (decided, 1190 m); A160 - A180 Port of Immingham Improvement (decided, 1481 m); Viking CCS Pipeline (decided, 1941 m); H2East Pipeline: Humber to Nottinghamshire (at pre-application, 114 m); Humber Carbon Capture Pipeline (at pre-application, 700 m); Stallingborough Combined Cycle Gas Turbine (CCGT) generating plant and Carbon Capture Plant (CCP) (at pre-application, 1333 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the North Killingholme built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in North Lincs - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full planning permission
Postcode
DN40 3JY
Received
5 Jun 2026
Validated
5 Jun 2026
Ward
Ferry
Parish
North Killingholme
Case officer
Show

Decision outlook

Day 126, past the statutory target. 88% of full applications in North Lincs are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 2 Oct 2026.

Day 12615 days to the predicted decision (day 141)
65%decided within 8 weeks
90%approved
86decided in the last year

Plota live figures for full applications decided by North Lincs in the last twelve months, from validation. North Lincs decision record →

Consultation & key dates

Comments by
23 Oct 2026
North Lincs
Planning Authority Score
4.6/10
Below average
#169 of 296 councils
Relevant to this application:
Householder decisions

North Lincs ranks #123 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (91%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
North Lincs decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #195 of 296
91%
Householder approved
Above avg (90%) #177 of 296
70%
Decided in 8 weeks
Above avg (63%) #123 of 296
44%
Extended time limit
Above avg (41%) #182 of 296
70%
Minor dwellings approved
114 decided (1-9 homes)
79%
Major dwellings approved
14 decided (10+ homes)
78%
Change of use approved
37 decided
705
Total decisions
96 refused in the year to March 2026