Quarry operations extension at Trearne Quarry, Gateside, Beith

Summary of planning committee decision

Decided by North Ayrshire Planning Committee on 26 Aug 2026.

26/00363/PPApproved

What was proposed

The application sought to extend quarrying operations for three years until 24 May 2029, followed by two years of restoration.

“Variation of condition 1 of planning permission N/23/00190/PP to extend quarrying operations until 24th May 2029”

“The application therefore seeks permission to extend the timescale for quarrying operations by a further three years until 24th May 2029. Thereafter, a further two years is requested for restoration of the land until 24th May 2031.”

Officer report

The site and its history

The quarry lies near Beith and Gateside, has operated since 1967, and its current operating and restoration conditions were granted in 2023.

“Trearne Quarry is located approximately 2km east of Beith and within 1km of Gateside. It contains reserves of limestone. Although quarrying at Trearne dates back to 1967, the current operating conditions, including a restoration scheme, were granted by the Council on 24th May 2023 under planning permission ref. 23/00190/PP.”

Officer report

Consultation responses

Transport officers raised no objections, environmental health officers supported the proposal subject to existing controls, and the community council made no comments.

“NAC Active Travel & Transportation - no objections.”

“NAC Environmental Health - no objections subject to the previous conditions continuing to be implemented on matters such as dust control, noise and vibration.”

Officer report

What was objected to

One objection concerned the site access, possible pollution, noise and dirt, while officers said conditions would address these issues and blasting would stop.

“Object to the proposed site access opposite the dwelling at Hessilhead Cottage. There are two other access routes which could be used instead. In the event that the proposed access route is used, it is requested that a wheel wash is installed to ensure clear roadways.”

“Response: Working hours have been specified in the application and would be regulated by condition. It is not proposed to alter the previously consented working hours. As per previous consents, there are conditions proposed to address noise impacts. As a result of changes to working practices, it is not proposed to undertake any blasting operations. This would be regulated by a condition.”

Officer report

Who spoke

No deputation requests were received for the application.

The committee vote

The committee unanimously approved planning permission following a motion by Councillor Foster, seconded by Councillor Stalker.

“Following a motion by Councillor Foster, seconded by Councillor Stalker, the Committee unanimously agreed to approve planning permission subject to the following conditions:”

Minutes

What was decided

Permission was approved with conditions requiring quarrying to end by 24 May 2029, restoration by 24 May 2031, and controls on operations and environmental impacts.

“That all quarrying operations at the site shall be discontinued within 3 years of 24th May 2026 (i.e. 24th May 2029) and the entire site shall be restored within a further 2 years (i.e. 24th May 2031) in accordance with the approved restoration scheme (as required under the periodic review of minerals consent 15/00573/DCMS) and to the satisfaction of North Ayrshire Council as Planning Authority.”

Minutes

The members' reasons

“The Committee noted that no deputation requests were received in respect of this application.”

Minutes

Approved subject to 1 condition, set out in the minutes.

Source: the council's minutes, quoted word for word.

Councillors at the meeting

Source: Plota analysis of the council's minutes; parties from Democracy Club.

Sources

  • North Ayrshire Planning Committee minutes, 26 August 2026
  • Agenda and papers (council website)

Source: Plota analysis of North Ayrshire's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Wednesday 26 August 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Vote
Unanimous
Councillors
9Conservative 3SNP 3Labour 2Independent 1Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

16 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →