School access condition variation at Site On Gortgonis Road Coalisland adjacent to Sports Field and Occupied By existing Community Center

Summary of planning committee decision

Decided by Mid Ulster Planning on 7 Jul 2026.

LA09/2026/0552/FApproved

What was proposed

The application sought to vary condition 4 so construction could begin before the new accesses were complete, allowing the school to open in September 2027.

“LA09/2026/0552/F ACKN Development Management Officer Report Committee Application Summary Committee Meeting Date: 7 July 2026 Item Number: 5.19 Application ID: LA09/2026/0552/F Target Date: 9 September 2026 Proposal: Application ref LA09/2018/1384/F . We wish to vary condition 4 to allow the development to commence before completion of the new accesses. The school is to open in Sept 2027.”

Officer report

The site

The site is on Gortgonis Road beside sports fields and an existing community centre, with access proposed from the road through an existing entrance.

“Case Officer Report Site Location Plan This material is based upon Crown Copyright and is reproduced with the permission of Land & Property Services under delegated authority NIMA CS&LA581 from the Controller of Her Majesty’s Stationary Office © Crown copyright and database rights.”

“The site is adjacent to two playing fields, one large grass pitch and a smaller 5 a side type facility. In addition, the larger playing field is surrounded by a surfaced running track. To the NE is a large area of woodland which was designated within the Area Plan as community woodland (CCW 01). Planting has taken place, as proposed, to allow for passive recreational purposes.”

Officer report

Earlier planning approvals

The earlier school approval allowed a primary school, nursery and playground, while related approvals covered enabling works and leisure-centre redevelopment.

“Site History LA09/2018/1384/F – Approval granted 26 th July 2022 for ‘Demolition of existing building to erect 7 based primary school (single unit), nursery single unit) and playground. The access road is existing to the site and will form part of another planning application submitted by Mid Ulster Council.”

“It is proposed to replace the existing pitch with floodlit 3G synthetic pitch and 6 lane running track with outdoor play areas. The site works to the new centre and recreation facilities include modification and improvement of the existing vehicular entrance, the addition of a right-hand turn land, car parking, pavements, fencing and amenity lighting. Relevant Policies Dungannon and South Tyrone Area Plan 2010”

Officer report

Why officers supported it

Officers considered that construction of the access and school needed to run in parallel because cable relocation would delay the access works.

“06 Rev 1 bearing the date stamp 04 March 2022, and shall be permanently retained thereafter. The area within the visibility splays and any forward sight line shall be cleared to provide a level surface n higher than 250mm above the level of the adjoining carriageway and such splays shall be permanently retained and kept clear thereafter.”

“If the school is to open in the new academic year works to form the access and new buildings will need to initially run parallel. DFI Roads were asked to comment on this variation of condition and they responded on 03.06.2026 suggesting an alternative condition stating: ‘The development hereby approved shall not become operational until the vehicular accesses, including visibility splays, any forward sight distance and right turn lanes, have been in accordance with…”

Officer report

Committee consideration

Members considered the circulated planning report, which recommended approval.

“Members considered previously circulated report on planning application LA09/2026/0552/F which had a recommendation for approval.”

Minutes

The committee vote

The application was proposed, seconded and approved subject to conditions set out in the officer’s report.

“Proposed by Councillor Carney Seconded by Councillor Kerr and Resolved That planning application LA09/2026/0552/F be approved subject to conditions as per the officer’s report.”

Minutes

The decision

Permission was granted to vary condition 4, with the development unable to become operational until the required vehicular accesses and visibility works were provided.

“Reason: To ensure compliance with Planning Approval LA09/2018/1384/F Condition 2 The development hereby approved shall not become operational until the vehicular accesses, including visibility splays, any forward sight distance and right turn lanes, have been provided in accordance with application LA09/2018/1329/F. Drawing No. 06 Rev 1 bearing the date stamp 04 March 2022, and shall be permanently retained thereafter.”

Officer report

Councillors at the meeting

The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.

Proposed by Councillor Eimear Carney, seconded by Councillor Dan Kerr.

Source: Plota analysis of the council's minutes; parties from Democracy Club.

Sources

  • Mid Ulster Planning minutes, 7 July 2026
  • Agenda and papers (council website)

Source: Plota analysis of Mid Ulster's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Mid Ulster
Date
Tuesday 7 July 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
15Sinn Féin 6DUP 3Independent 2SDLP 1UUP 12 otherShow votes
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

292 decisions in the 12 months to this meeting, 11 against officer advice.