Electricity cable network upgrade at Land Along The A483 Corridor, Porthmadog

Summary of planning committee decision

Decided by Gwynedd Planning Committee on 28 Sept 2026.

C25/0946/44/EIAApproved

What was proposed

The scheme would upgrade electricity infrastructure, install replacement underground cables, extend Wern, build Minffordd facilities and remove the existing Garth compound.

“Proposal: The extension of the existing Wern Cables Sealing End Compound (CSEC) including a new permanent access; a new Minffordd CSEC and Tunnel Head House (THH) with permanent access; the removal of the existing Garth CSEC; installation of new 400 kilovolt (kV) cables to replace redundant 400 kV and 132 kV cables; and other associated infrastructure and ancillary works.”

“Description: 1.1 This is an application for the extension of the existing Wern Cables Sealing End Compound (CSEC) including a new permanent access; a new Minffordd CSEC and Tunnel Head House (THH) with permanent access; the removal of the existing Garth CSEC; installation of new 400 kilovolt (kV) cables to replace redundant 400 kV and 132 kV cables; and other associated infrastructure and ancillary works.”

Officer report

The site and route

The 106.4-hectare route extends about six kilometres between Wern and Minffordd, crossing roads, railways, the Glaslyn SSSI and other infrastructure.

“The proposed works included in this application covers a 106.4 ha and extends for approximately 6 km, between the Wern CSEC and Minffordd broadly following the corridor of the A487 Porthmadog Bypass, which runs in a generally east-west direction.”

“Progressing from west to east, the route passes through the Porthmadog Roundabout, beneath the A487 Porthmadog Bypass, and crosses both the Welsh Highland Heritage Railway (WHHR) and the Ffestiniog & Welsh Highland Railway (FfWHR). It continues to the north of Clwb Chwaraeon Madog before turning south and passing beneath the A487 Porthmadog Bypass once again.”

Officer report

What officers recommended

Officers recommended approval because the scheme supports network resilience, renewable energy and energy security, while conditions would control its environmental effects.

“Conclusion: 6.1 The proposed development forms part of the nationally significant Pentir to Trawsfynydd Reinforcement Project and would facilitate the replacement and modernisation of existing electricity transmission infrastructure between Wern CSEC and Minffordd CSEC. The scheme would increase energy network’s resilience, support wider renewable energy generation and contribute towards national energy security objectives.”

“No. Subject Brief Summary 1 Time Limit Development must commence within 5 years of the permission date. 2 Approved Plans Development to be carried out in accordance with the approved plans and documents. 3 Working Hours Restricts construction working hours and controls out-of-hours operations. 4 Piling Requires non-percussive piling methods and restricts piling hours.”

Officer report

Concerns from residents

Public objections concerned business access, construction traffic, noise, disturbance, dust, lighting, vibration, heritage, information gaps and economic effects.

“Public Consultation A notice was placed in the press; notices were placed in several locations close to the site and nearby residents were informed. Comments have been received from the public objecting on the following grounds; Objection on planning grounds; • Object if the development/construction works would result in the closure of vehicular access to businesses.”

“Concern regarding the alignment of the track from the A498 to the CSEC and the disturbance and noise arising from it. • Impact on listed building setting: Harm to the setting and tranquillity of a Grade II* listed building, contrary to heritage protection policies. • Lack of information: The application fails to provide essential details on noise, vibration, traffic, timing, duration and mitigation, preventing proper assessment by the Local Planning Authority.”

Officer report

Who spoke

A speaker for the applicant supported the scheme, while two local members highlighted ecology, construction impacts, playing-field restoration and cable safety concerns.

The decision

“To approve with conditions 1. Time Limit The development must commence within 5 years of the date of the permission. 2. Approved Plans The development to be carried out in accordance with the approved plans and documents. 3. Hours of Work Limits construction work hours and manages out-of-hours operations. 4. Piling Requires non-percussive piling methods and restricts piling hours. 5. Lighting Requires approval of a lighting scheme to protect bats and control light spill before operational lighting is installed. 6. Enclosures Requires approval of colours and finishes for fences, walls, gates and other boundary treatments. 7. Contamination Requires investigation and remediation of any previously unidentified contamination encountered during development. 8. Flood Mitigation Requires approval and implementation of a temporary flood mitigation scheme for cons”

Minutes, 28 Sept 2026

Councillors at the meeting

The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.

Apologies Huw Rowlands Plaid Cymru, Delyth Lloyd Griffiths Plaid Cymru

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Gwynedd Planning Committee minutes, 28 September 2026
  • Agenda and papers (council website)

Source: Plota analysis of Gwynedd's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Gwynedd
Date
Monday 28 September 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
13Plaid Cymru 8Independent 3Gwynedd First 11 otherShow votes
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

48 decisions in the 12 months to this meeting, 4 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →