Station Street Nottingham Nottingham City NG2 3NG Data via plota.co.uk

26/00585/PFUL3 - Full planning application Approved

Proposal

Full planning permission for the relocation of a section of the existing district heat network steam main and electrical cabling, installation of additional district heating pipework and electrical cabling, the construction of associated pipe gantry, new services bridge across the Nottingham-Beeston Canal and associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

Received
16 Apr 2026
Consultation
29 Jun 2026
Approved
31 Jul 2026

Approved on 31 Jul 2026 · Committee Decision · Last checked 31 Jul 2026

Documents 30

All documents on the council site ↗

Site constraints 5

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Station conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Heritage at risk: The Station, Nottingham
On the register of historic places assessed as at risk.
A designated building, monument, park or conservation area assessed as at risk from neglect, decay or development. Proposals that secure its future are looked on favourably.
Historic England ↗
Air quality management area: AQMA No.2
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Also on the record
Inside the Nottingham built-up area.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 11 September 2026. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Nottingham - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Nottingham
Application type
Full planning application
Postcode
NG2 3NG
Received
16 Apr 2026
Validated
16 Apr 2026
Ward
Castle (May 2019)
Case officer
Show
Target decision
11 Jun 2026
Decision
Grant conditional permission
Decision date
31 Jul 2026
Decision level
Committee Decision
Applicant
Show
Agent
Thomas Lord

How this decision compares

Decided in 106 days from validation, 50 days slower than Nottingham's median of 56 for utility and infrastructure works. Approved, as 96% of utility and infrastructure works here are.

52%decided within 8 weeks
96%approved
28decided in the last year

Plota live figures for utility and infrastructure works decided by Nottingham in the last twelve months, from validation. Nottingham decision record →

Public comments

No public comments yet.

Last counted 31 Jul 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14860919
Consultation
29 Jun 2026
Comments by
27 Jul 2026
Site or press notice
1 May 2026
Env. assessment
No
Nottingham
Planning Authority Score
4.1/10
Below average
#191 of 296 councils
Relevant to this application:
Householder decisions

Nottingham is slower than most councils at deciding householder applications, ranking #255 out of 296. Householder applications are slightly more likely to be approved here (90%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Nottingham decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #139 of 296
90%
Householder approved
Above avg (90%) #193 of 296
45%
Decided in 8 weeks
Below avg (63%) #255 of 296
33%
Extended time limit
Below avg (41%) #79 of 296
80%
Minor dwellings approved
44 decided (1-9 homes)
95%
Major dwellings approved
21 decided (10+ homes)
82%
Change of use approved
99 decided
1,044
Total decisions
116 refused in the year to March 2026