What was proposed
The application proposed twelve frameless black solar panels on the south-western lean-to roof over the outside seating area.
“PEMBROKESHIRE COAST NATIONAL PARK AUTHORITY DELEGATED DECISION REPORT Re f No: NP/26/0242/FUL Proposal: Proposed PV Panels to roof over outside seating area Site Location: The Shed Tea Room, Porthgain, Haverfordwest, Pembrokeshire, SA62 5BN Recommendation: Approve, subject to conditions This application is being considered by the Development Management Committee, in accordance with the scheme of delegation because the building is owned by the National Park Authority.”
“Porthgain Conservation Area SPG C onstraints • Biodiversity issue • Ancient Monument – within 500 m • Landscape Character Area • Conservation Area – Porthgain • Setting of listed buildings • Heritage coast – within 100 m • Safeguarding zone • Potential for surface water flooding • LDP Centre boundary - Porthgain • Rights of way inland – within 50 metres • Flood risk O fficer’s Appraisal 1.Site and Proposed development The S hed Tea Room is a lean-to structure at the west…”
Officer report
Earlier changes
The site has a history of permissions for restaurant, staff-area, cladding, window, path and covered-seating works, with related listed building consents.
“The proposal comprises the addition of solar PV panels to the south-western lean-to. The panels – twelve in total – are all-black and frameless. The panels are configurated in a single block covering the majority of the roof, surface mounted on corrugated steel sheeting. The s cheme is in keeping with the character of the listed building, and its setting in terms of design and form.”
“NP/11/228. Extension to provide staff area. Planning permission granted 26/07/11 • NP/11/229. Extension to provide staff area. Listed building consent granted 15/08/11 • NP/16/0394. Addition to existing extension to provide staff area. Planning permission granted 7/09/2016 • NP/16/0395. Addition to existing extension to provide staff area.”
Officer report
The officer recommendation
Officers recommended approval because the scheme was appropriately designed, supported energy efficiency and complied with relevant development plan policies.
“Overall, the proposed development is considered acceptable in terms of its impact on biodiversity, as such is considered to comply with policy 11 of the LDP2 4.C onclusion 192.The proposal is appropriate in terms of size, scale and detail and will result in energy efficiency measures being introduced to support an existing facility within a Rural Centre. The proposed development is considered to comply with relevant National and Local Development Plan policies.”
Officer report
Responses to the application
The community council, Natural Resources Wales and Cadw raised no adverse comments; an ecologist suggested a condition, and no third-party representations were received.
“No adverse comments have been raised by consultees, and no third-party representations have been received. The proposed scheme is considered in keeping with the character of the listed building, and its setting in terms of design and form. The proposal complies with relevant policies contained in National and Local Development Plans. As such, the application can be supported subject to conditions A recommendation for approval is made, subject to suitably worded conditions.”
“Public Response A site notice and neighbour notification letters were posted in accordance with requirements of the Town and Country Planning (Development Management Procedure) (Wales) Order 2012. No third-party representations have been received.”
Officer report
The committee discussion
A member asked whether the panels would affect lighting levels, and the officer said no additional lighting was proposed.
“No adverse comments had been raised by consultees, and no third-party representations had been received. The proposed scheme was considered to be appropriate in terms of size, scale and detail and in keeping with the character of the listed building, and its setting in terms of design and form. It would result in energy efficiency measures being introduced to support an existing facility within a Rural Centre.”
“One Member asked whether the introduction of PV panels would impact on lighting levels within the structure, and the officer replied that no additional lighting had been sought as part of the application. The recommendation of approval was proposed by Councillor Clements, seconded by [name withheld] and carried at the vote.”
Minutes
The vote and decision
The approval recommendation was proposed, seconded and carried, and the application was approved subject to time, approved-plan, planting and seeding conditions.
“Decision: That the application be approved subject to conditions in relation to the time of the development, accordance with approved plans and documents and planting and seeding.”
Minutes
Sources
- Pembroke Coast Development Management Committee minutes, 15 July 2026
- Agenda and papers (council website)
Source: Plota analysis of Pembroke Coast's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Pembroke Coast
- Date
- Wednesday 15 July 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Pembroke Coast committee decisions →
This committee's year
23 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.