Community hall extension at Carstairs Junction Hall, Carstairs Junction
Summary of planning committee decision
Decided by South Lanarkshire Planning Committee on 8 Sept 2026.
What was proposed
The application proposed a single-storey rear extension with enlarged meeting rooms, a kitchen and internal changes including soft play and sensory rooms.
“Description of Proposed Development 3.1. Planning permission is sought for the erection of a 30m x 5.4m single storey extension to the rear of the hall. This would enlarge the existing 277sqm footprint by an additional 166sqm. The eaves height of the extension would reach 2.6m (h), with its lean-to-roof rising to a maximum height of 3.8m (h) where it connects into the existing dual pitch roof.”
“a soft play area • a seating area • the existing meeting rooms would be converted into sensory rooms • the toilets area would be retained • the existing kitchen would be adapted into a food preparation area…”
Officer report
The site
The hall is a single-storey timber-clad building in a parkland setting, with parking, pedestrian access and photovoltaic panels.
“Site Description 2.1. The application site extends to approximately 0.567ha. The site sits within the Carstairs Junction settlement, and a lease for the community hall building was acquired under the CAT/25/0004 community asset transfer application that was passed by the Housing and Technical Resources Committee on 8 October 2025.”
“Carstairs Junction Hall is a single-storey gable ended building, that sits within a parkland setting. Its external walls are clad in timber with a facing brick basecourse below, and it has photovoltaic panels located upon its profile concrete tile roof. Off- street vehicle parking on a hard surfaced area to the front of the building, and pedestrian access to the hall can be accessed from St Charles Avenue.”
Officer report
Officers’ recommendation
Officers recommended permission because the proposal supported continued community use, fitted the settlement and would not adversely affect residential amenity or the building.
“Principle of Development Policy 9 of NPF4 identifies that proposals for the re-use of derelict buildings will be supported where the reuse would be sustainable. The building would continue its use as a community hall and the current proposal will ensure it can continue to provide services as a community hub. Most of the surrounding greenspace will remain undeveloped and the area will continue to function as a public park.”
“Policy 27 of NPF4 seeks to encourage, promote and facilitate development in our cities and towns. The policy establishes that development proposals that enhance and improve the vitality and viability of cities, towns and local centres will be supported. The application would enhance the building and its potential for community use. The mix of uses at the site could bring additional footfall to the wider settlement area making it a more sustainable settlement.”
Officer report
Consultation responses
The archaeological service and roads team raised no objection to the proposal.
“Consultations 6.1. West of Scotland Archaeological Service – No objection to proposal Response: Noted…”
Officer report
Public views
Six objections and six supporting representations were received, raising concerns about greenspace, noise, amenity, traffic, need and nesting, alongside community benefits.
“Representations 7.1. Following the statutory periods of neighbour notification and advertisement, 6 objections have been received, and 6 in support. The issues raised are summarised as follows:-”
“Design and Amenity Issues • Loss of greenspace • Noise impact • Impact on the amenity of neighbouring dwellings • Use of surrounding land for the extension • Excessive size of proposed kitchen…”
Officer report
Committee discussion
Members discussed the application, and an officer undertook to find out whether the development would meet developer funding criteria.
“There followed a discussion on the application during which an officer undertook to find out if the development would meet the criteria for developer funding.”
Minutes
The committee’s decision
The committee granted planning permission subject to the condition specified in the officer report.
“The Committee decided: that planning application P/26/0396 by Soul of the Junction for the erection of a single storey rear extension and associated alterations at Carstairs Junction Hall, 20 St Charles Avenue, Carstairs Junction be granted subject to the conditions specified in the Executive Director’s report.”
Minutes
The condition
The development must begin within three years of the date planning permission is granted.
“Grant full planning permission subject to conditions:-”
“The development to which this permission relates shall be begun no later than the expiration of three years beginning with the date of grant of this decision notice.”
Officer report
Councillors at the meeting
- Richard NelsonChairConservative
- Gerry ConveryVice-ChairLabour
- Alex AllisonConservative
- Ralph BarkerDeclared an interest and left for this itemLabour
- Archie BuchananSNP
- Ross ClarkSNP
- Margaret CowieLab Co-op
- Colin DewarSNP
- Alistair FultonSNP
- Celine HandibodeLabour
- Cal Johnston-DempseySNP
- Davie McLachlanLab Co-op
- Norman RaeLib Dem
- Mo RazzaqLabour
- John RossSNP
- Graham ScottLabour
- David ShearerSNP
- Helen TonerSNP
- David WatsonIndependent
- Kirsty Williams
- Gladys Ferguson-MillerSubstitute for Graeme Horne
- Julia MarrsSubstitute for Mary DonnellySNP
Apologies Maureen Devlin Labour, Mary Donnelly SNP, Graeme Horne SNP, Ross Alexander Lambie Conservative, Martin Patrick Lennon Labour
Source: Plota analysis of the council's minutes; parties from Democracy Club.
Sources
- South Lanarkshire Planning Committee minutes, 8 September 2026
- Agenda and papers (council website)
Source: Plota analysis of South Lanarkshire's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- South Lanarkshire Planning Committee
- Council
- South Lanarkshire
- Date
- Tuesday 8 September 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Councillors
- 21SNP 9Labour 4Conservative 2Lab Co-op 2Independent 1Lib Dem 12 otherShow councillors
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- South Lanarkshire committee decisions →
This committee's year
87 decisions in the 12 months to this meeting, 1 against officer advice.